BPCS/LX Tip of the Week: Indirect Time Reporting

In Infor LX, there are two ways to enter indirect labor. You can use either SFC600 or SFC650.

  • If you use SFC600 and enter a reason code for the indirect labor, the reason you entered is written to the Labor Ticket file.
  • If you use SFC650 and enter a reason code for the indirect, the reason code is not written to the labor Ticket file.

In either case, the reason code is not validated from the transaction file because there is no indirect transaction code. The indirect code that can be setup is machine downtime. If you need to validate and track indirect by reason and validate the reason code, then you may want to explore an MES solution that works with Infor LX.

 

Previous Article Baan/LN Tip of the Week: Differences Between Constraint Planning in Baan IV and Enterprise Planning in LN
Next Article What You Don’t See Can Hurt You
Print
35991 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

This is a simple way to go from the customer order to making the order and shipping the order. It involves a few simple steps:

  1. Receive and enter the customer order
  2. Automatic credit review
  3. Automatic release of the shop order tied to the customer order
  4. Issue material, report labor to the production order receipt
  5. Pick the order, ship the order, invoice the customer

With lean, you can skip processing the demand through MRP. You can go directly from the customer order to the shop order creation.

First149150151152153154155157

Theme picker

Tips: LN | Baan

Table Timestamp Definitions (ttadv4136m000)

Use this session to define timestamps for Infor LN tables. A timestamp is an additional column that stores the date and time of the last change for each record.

Timestamps are utilized by features like the extraction logic of CPM Enterprise Analytics. They enable CPM to perform incremental data extractions. For example, CPM can use the timestamps to extract records that were changed during the last week in a weekly extraction process.

To Create Timestamps...

Operations: To absorb the cost of cost items into specific projects, you'll need to handle them as customized items. However, cost items cannot directly be defined as customized items. Customized items must be physical, either manufactured or purchased.

That said, it's still possible to absorb cost items into a project, although indirectly. Here's how:

  1. Set Up Ledger Account: First, create a new ledger account in session tfgld0508m000 and set the type to "PCS" (project) in the operations management integrations. This account will be used for matching and approving purchase orders for cost items.

  2. Create and Activate Projects: Ensure that the necessary projects are created and set to active status.

  3. Purchasing Cost Items...