Baan/LN Tip of the Week: Default Order Frequency

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders. For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In ERP LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period. For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

Previous Article The Value of Upgrading Your ERP – Maintaining Modern Technology
Next Article BPCS/LX Tip of the Week: Is Lot Control Necessary?
Print
48853 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

In the master schedule creation, you have the flexibility to enter a planning start date, or default to the facility planning start date. Infor LX uses the planning date to plan both orders with forecasts and customer orders as demand.You can create your master schedule from the Master Production Scheduling module (MPS).

These programs are used to capture and post shop floor information. Labor reporting, machine time, etc. can be captured by either program. The key difference is that one will also capture the production receipt and backflush components. Based on your company information / transaction process, one of these programs will most likely be used daily to capture current shop floor data. You can use the shop packet labor ticket for the manual recording, and the keying of the data. Alternatively, you can incorporate an automated method like an MES solution to capture the data and streamline the process.

First153154155156158160161162

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

1345678910Last

Theme picker

Categories