Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Kathy Barthelt

Infor LN & Baan Tip of the Week: Dynamic Assembly Control BOM (LN 10.7)

In previous releases of LN, the Assembly Control Bill of Material (BOM) offered limited flexibility. For each end item configuration, users were required to create unique Engineering Modules, which are used to determine the assembly parts that are consumed in a specific Line Station during a specific operation.

If LN is integrated with Design Studio, previously called Infor CPQ, BOM structures can be maintained in Design Studio for Assembly Control. These structures can include non-configurable parts that are directly linked to configurable items. When communicating these structures to LN using the Assembly Control, Product Variant Structure (tiapl3510m000) session, the structures were rejected because non-configurable parts were not supported by the session logic.

In this release, BOM structures that include non-configurable parts can now be accepted in LN. Consequently, if LN is integrated with Design Studio, it is no longer required to use the Engineering Module. Using the Engineering Module has become optional.

Previous Article Infor LX & BPCS Tip of the Week: Multi-Level Backflush (LX 8.4)
Next Article Tip of the Week: 8 Ways to Improve Production Efficiency in Your Manufacturing Plant
Print
53018 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

When I try to enter a 3-way match invoice with zero cost items, I get an error 'Must have value/cost entry.

Resolution
​ACP500 requires a positive value to create a 'C' transaction when entering a 3-way match invoice. If you are receiving inventory items for free (no charge) and have a purchase order for it and need to include the quantity in inventory, you should first receive your items through PUR550 using something like a 'U' transaction. Then, you would enter a 'C' transaction with the quantity and zero cost through PUR550. This will change the status of the line in the HPO file to '3', fully received and costed. Once this is completed, you will be able to enter an invoice for your zero-cost item through ACP500 without getting the error message 'Must have value/cost entry.

First1415161719212223Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

1345678910Last

Theme picker

Categories