Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

George Moroses
/ Categories: Infor LX & BPCS Tips

Infor LX & BPCS Tip of the Week: MPS vs. MRP

What items should be MPS planned, and what items should be MRP planned…

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor/ERP LX will calculate cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.
Previous Article You’ve got a handle on your inventory requirements, right? Are you confident you can handle a rush order, or ten rush orders?
Next Article Consulting News: How do I identify the processes that impact my ERP upgrade?
Print
40495 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The cycle counting sub-system in Inventory Management determines which items are selected for cycle counting based on the following criteria:

  1. Cycle Counts/Year: The system calculates the cycle count frequency for each item using the "Cycle Counts/Year" field in the Item Master file (optional).

  2. Last Cycle Count Date: If you use locations, this date is found in the Location Inventory file (ILI), and if you don't, it's in the Warehouse Inventory file (IWI).

The system adds the calculated cycle count frequency to the last...

WebTop release 4.8 is NOW AVAILABLE for Infor LX versions 8.3.5 and 8.4.x.

WebTop is a web interface based on green screen code automatically generated using a tool called 'WebTop Studio'. The process of generating the web interface is referred to as "Weblication".

Infor is focused on modernizing and web-enabling Infor LX and this release provides significant improvements to the web-based user experience.
Key features:

  • Grid decorators for advanced customization
First1516171820222324Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

1345678910Last

Theme picker

Categories