OTTO: Making plans happen isn’t just about monitoring material shortages

Making plans happen isn’t just about monitoring material shortages. Supporting activities can be the real cause of delays. Some non-material events customers have monitored using OTTO include:

  • Scheduling and coordination of outside services (such as heat treating and plating)
  • Quality Assurance for pharmaceuticals and inspection
  • Moving off-site inventory to the plant
  • Moving inventory from temporary (conveyor) location to pickable location
  • Scheduling of overseas containers
  • Design engineering for make-to-order

OTTO provides the ability to proactively manage the entire customer order backlog from top to bottom. It begins monitoring orders as soon as they’re booked and identifies and prioritizes those critical events that must happen every day so they can be managed and get orders produced and shipped on time.

Visit Our OTTO page to learn more.

Previous Article How Do I Determine If MES Is Right For My Business?
Next Article Anxious to learn more about IDF? Attend Inforum Sessions highlighting the latest and greatest updates
Print
22121 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

What items should be MPS planned, and what items should be MRP planned?
Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor LX (ERP LX) will calculate the cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.
First2324252628303132Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

1345678910Last

Theme picker

Categories