Infor LN & Baan Tips & Tricks for EXECUTIVES:

OPERATIONS: Order Quantity Dependent Routings vs Default Routings
Order quantity-dependent routings
An automatically selected routing tailored to a specific production order quantity is useful. An example would be if the production order quantity is large, a routing with high production rates is used; If the order quantity is small, another routing is selected.

You can set up these quantity-dependent routings:

  • Select the Quantity-dependent Routing check box in the Item - Production (tiipd0101m000) session.

  • Enter the routing codes in the Item - Routings (tirou1101m000) session. Enter the maximum quantity for which a routing is valid in the Up to Quantity field.

Note: If multisite functionality is activated, the routings available may vary per site on the job shop bill of material selected. Differences in routings have an impact on the standard cost calculation.

Default routing

If the Quantity-dependent Routing check box is not selected, the default routing applies to an item. However, this default routing must also be linked to the item. To find out, LN checks the default routing code in the Default Routing field of the Job Shop Master Data Parameters (tirou0100m000) session. Next, LN checks whether the default routing code is linked to the item in the Item - Routings (tirou1101m000) session. If so, the default routing applies to the item. If the default routing is not linked to the item, no routing is used.


FINANCE: Integration Transactions - Compression
Integration transactions can be compressed before they are posted. For each integration document type, you can indicate whether the debit transactions and/or the credit transactions must be compressed.

Transactions can be compressed if the following transaction details have the same value:

  • The source financial company.

  • The destination financial company.

  • The transaction type and series.

  • The ledger account and dimensions.

  • The transaction currency.

  • The fiscal year and the financial period, the tax period, and the reporting period.

  • The integration document type and the Debit/Credit indicator.

  • If related gain and loss transactions are generated, the same compression criteria are used to compress these.

Note: Intergroup transactions are not compressed.

 
TECHNOLOGY: Infor LN Rest API

Frequently Asked Questions (KB2316174)

For Infor LN a framework has been developed to support REST API-based services for lean integrations. This framework is now made available for the LN application. This KB answers some common questions you may have and procedures that are needed for using the LN Rest APIs.

More details on these topics can be found in the Infor LN REST API Administration Guide.

Previous Article Infor News You Can Use: Discover the Power of Advanced Planning & Scheduling with industry expert Greg Keating
Next Article Infor News You Can Use | Why Upgrade to Infor LX in the Cloud
Print
6734 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

What items should be MPS planned, and what items should be MRP planned?
Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor LX (ERP LX) will calculate the cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.
First2324252628303132Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

1345678910Last

Theme picker

Categories