Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Crossroads RMC
/ Categories: Event / News

Crossroads RMC to Exhibit at Inforum 2016

Inforum 2016  returns as a three and a half-day event of educational seminars and workshops focused on the future of enterprise software and your business. This event is Infor’s premier event for 2016, and Crossroads RMC is excited to sponsor the event! Come see us in Booth 173 to learn about Crossroads MES and Analytics Dashboard solutions for the shop floor, our Services for Baan/LN and BPCS/LX, and see a demo of our latest solution, Analytics Dashboard, which can be connected to any ERP to provide up to the minute sales analysis data.

    

Previous Article If ERP is plumbing for the Enterprise - How do we unplug it and keep it from making a huge mess?
Next Article Tip of the Week: 8 Common-Sense Rules for Inventory Management
Print
24672 Rate this article:
No rating
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

What items should be MPS planned, and what items should be MRP planned?
Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor LX (ERP LX) will calculate the cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.
First2324252628303132Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last

Theme picker

Categories