Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

George Moroses
/ Categories: Infor LX & BPCS Tips

Infor LX & BPCS Tip of the Week: MPS vs. MRP

What items should be MPS planned, and what items should be MRP planned…

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor/ERP LX will calculate cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.
Previous Article You’ve got a handle on your inventory requirements, right? Are you confident you can handle a rush order, or ten rush orders?
Next Article Consulting News: How do I identify the processes that impact my ERP upgrade?
Print
40547 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Spreadsheets are often the tool of choice for many organizations to store and arrange information for financial planning, analytics, compliance, and more. Ironically, for many business processes that involve managing data, it creates the exact opposite effect––silos of information and inefficiency. And because it stores organizational data in a readily sharable way, there is a high risk of exposing confidential information.

Read this Infor best practice guide to discover the top five business processes that a modern data and analytics architecture can automate and deliver far more value than spreadsheet-driven techniques.

Infor Best Practice Guide: 5 Ways Modern Analytics Reduces Spreadsheet Risk and Inefficiency

How do I know which orders are on hold? – Pick Release / Pick Confirm

Orders that are on credit hold, customer hold, user hold, margin hold, credit card hold, or pricing hold cannot be selected for Pick Release or Pick Confirm. The ORD952B, Orders Not Selected Report, can be requested at Pick Release or Pick Confirm to list any order that would normally qualify for selection, but has been excluded for other reasons, and to print that reason. ORD952B has been modified to validate the hold status of the original customer order, instead of the intercompany automation warehouse order that is being processed, and to print a reference to the original customer order along with the reason.

First2425262729313233Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

1345678910Last

Theme picker

Categories