Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Crossroads RMC

Infor LN & Baan | Infor LX & BPCS Tip: Time for the dreaded three words?

Manual     Physical     Inventory

While it may be accurate (and I say MAY), is a Manual Physical Inventory the right way? Best practices would say absolutely not!

The better way is implementing Cycle Counting. Why Cycle Counting instead of a full physical inventory? With a cycle count, the count focuses on a selected range of stock that can be carried out in parallel with a company’s normal operations. Cycle Counts represent a streamlined method of inventory management to ensure less disruption on the business processes associated with receiving, consuming, or dispatching of stock. 

The “freeze” is no longer required, your staff doesn't need to work long hours over the holidays, and you get accurate inventory counts all year long! Crossroads RMC can help you implement Cycle Counting efficiently and painlessly, contact us today to get started. 800.762.2077

Previous Article Infor LN & Baan Period End & Fiscal Year End Processing Checklist
Next Article Infor LX & BPCS Tip: What is IDF and Why Do I Need It?
Print
22195 Rate this article:
5.0
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Previously, Material Requirements Planning (MRP) preferred practices meant that the component's due date was the same as the parent's shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower-level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The Multi-Level Shop Order Release, SFC5302, has a new parameter for shop orders. The Due Date of Children = Release Date of Prent (Due Date of Children) field allows the user to set the due date determined for multi-level shop orders.

This feature uses different exchange rates in the user's inventory processes by using new macros in Post Inventory to G/L, INV920D. INV920 used macros limited by the Override Exchange Rate parameter set on the book in Book Definition, CEA105D3. If the Override Exchange rate parameter is set to No, the macro uses the Rate Type of the Book. If the Override Exchange parameter is set to Yes, the macro uses the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Warehouse Company, Order Company, or the Book regardless of the Override Exchange Rate parameter in the Book.

135678910Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

1345678910Last

Theme picker

Categories