Baan/LN Tip of the Week: Default Order Frequency

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

Previous Article 15 Myths About Warehouse Automation
Next Article BPCS/LX Tip of the Week: Establish Costing For Purchased Items
Print
46092 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The Cycle Counting Sub-System Within Inventory Management

The system uses the following information as the basis for cycle counting selection:

  • Cycle Counts/Year: The system calculates the time between cycle counts based on your entry in this Item Master file field for each item (optional).
  • Last Cycle Count Date: This date is in the Location Inventory file, ILI, if you use locations, or in the Warehouse Inventory file, IWI, if you don't.

The system adds the time between cycle counts (calculated as described above) to this date. If the result is less than or equal to today's date, the item is selected for cycle counting. If it is greater than today's date, the item is not selected, it is not due yet for cycle counting.

There is another special condition that causes an item to be selected for cycle counting. If the ILI/IWI record of the item has a Y in the Cycle Flag field, the item is selected automatically. This flag indicates that the item's on-hand balance has gone to a negative value sometime since the last cycle count. That applies even if the value is not negative at selection time. The programs that can set this field are INV500D, INV510, and BIL540.

You can also limit the items selected for counting by specifying limits of the item numbers or warehouses to be searched.

First2526272830323334Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements: