Infor LN & Baan Tip: What conditions must exist before changing an item's inventory unit?

Is there a procedure for changing an item’s inventory unit? What conditions must exist before it can be done?

Once inventory transactions (receipts or issues) have occurred for an item, the inventory unit cannot be changed. If only orders have been placed against the item (sales or purchase), the inventory unit can be changed if these orders are removed and the economic stock of the item is zero.

The reason that the inventory unit cannot be changed once transactions have been made is due to how transactions are recorded. The inventory transactions are recorded in units. These units are the inventory unit of the item. The inventory unit is not held in this table, however. The inventory unit is held on the item data. For example, if 5 pieces (pcs) of an item are issued and the inventory unit is later changed to pounds (lbs), there will be a mismatch in the inventory history of the item. In the past, the item was issued as pcs, and now the item master inventory unit is lbs. As the inventory unit is not date effective, the inventory has then been issued in two different units (pcs and lbs), but there is no method to recognize this difference.

Previous Article Infor LX & BPCS Tip: 4 Approaches to Customizing LX / BPCS - Preparing for a Future Upgrade
Next Article Reskilling and Upskilling Your Staff – Why You Shouldn’t Ignore This
Print
13832 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

This program allows maintenance of vendor terms, which you individually assign to each vendor. Vendor terms designate the due date and the discount date as a number of days after the invoice date. You establish the discount percentage here. Vendor terms are stored in the AVT file. Rather than use the method specified above, you can override due dates and discount dates so those calendar days are used to age invoices.

Access: Menu ACP02

Use this program to enter period overhead expenses to distribute to various work centers. You can set up this overhead cost allocation on either a per-hour or a per-piece basis, depending on the overhead allocation type specified for each work center on the Work Center Maintenance screen, CAP100D2-01. The system spreads the amounts entered across all shop orders posted by Shop Floor Posting, SFC600, or Production Reporting, JIT600, when you run Overhead Cost Allocation, CST510. The system stores allocated overhead in the Labor Ticket file, FLT, and updates actual item cost when you run Shop Order Close and Post, CST900.

Access: Menu CST

First2728293032343536Last

Theme picker

Tips: LN | Baan

Table Timestamp Definitions (ttadv4136m000)

Use this session to define timestamps for Infor LN tables. A timestamp is an additional column that stores the date and time of the last change for each record.

Timestamps are utilized by features like the extraction logic of CPM Enterprise Analytics. They enable CPM to perform incremental data extractions. For example, CPM can use the timestamps to extract records that were changed during the last week in a weekly extraction process.

To Create Timestamps...

Operations: To absorb the cost of cost items into specific projects, you'll need to handle them as customized items. However, cost items cannot directly be defined as customized items. Customized items must be physical, either manufactured or purchased.

That said, it's still possible to absorb cost items into a project, although indirectly. Here's how:

  1. Set Up Ledger Account: First, create a new ledger account in session tfgld0508m000 and set the type to "PCS" (project) in the operations management integrations. This account will be used for matching and approving purchase orders for cost items.

  2. Create and Activate Projects: Ensure that the necessary projects are created and set to active status.

  3. Purchasing Cost Items...