Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

George Moroses

Infor LX & BPCS Manufacturing Tip: Backward Scheduling

Operations are automatically backward scheduled at shop order release time. The backward scheduling algorithm starts with the shop order due date and schedules each operation based upon the standard move and queue times in the routings and the number of days the job is expected to run at standard. The system calculates and stores the operation scheduled start date. The dates may be modified by the shop order maintenance program. The number of days that a job is expected to run an operation is dependent upon the available capacity for that work center and the total hours scheduled for that operation.

The backward scheduling algorithm also considers the shop calendar for weekends, shutdowns, holidays, and partial days. Backward Scheduling Process The algorithm starts with the due date of the shop order or planned order. The system makes the following calculations for each operation in the reverse sequence:

1. The number of move days is subtracted from the due date (or initial date of the previous operation) to get the due date for this operation. The move days are only used on valid shop calendar days.

2. The system uses the following calculation for the number of clock hours for the operation: Standard run or machine hrs/No. of operators + setup hours

3. The number of clock hours is spread over the available daily capacity of the work center for those given days. The system uses the following calculation for the daily capacity of the work center: Number of shifts x hours per shift x average efficiency/100

4. Each day is checked against the shop calendar; the calculation bypasses inactive days or adjusts for any changes in the work center capacity for that day.

5. Queue time days are subtracted in the same manner as move time days. The resulting date is the operation start date.

The algorithm then goes to the previous operation. When all operations have been included, the resulting date is the scheduled start date of the shop order. Note that MRP uses the item lead time to determine material requirement dates on planned orders.

Backward scheduling is supported in all shop order release programs (SFC500, SFC550, and FAS510). Backward scheduling is recalculated if a shop order is maintained through SFC500 when the due date or the required quantity is changed; however, you cannot enter move and queue times through the maintenance program when adding an operation to the shop order.

Previous Article Infor LX & BPCS Tip: What is IDF and how could it make my life easier?
Next Article Infor LN & Baan Manufacturing Tip: All About Routings
Print
19461 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The Infor Development Framework (IDF) re-architects the way a user interacts with the application, providing an efficient, task-oriented process to view application information that is contained within Infor LX. IDF enables users to configure their view of the application data without modifying the core application and its supportability.

The examples below describe how users can configure their display of data and maximize overall productivity:

  • Arrange application information into multiple groupings and sequences that make sense for the job.
  • Filter or hide records to show only the information that applies to the job or task that the user is performing.
  • Customize the information for an individual user, a group of users, or all users.

Infor’s Intelligent Open Network (ION) technology easily integrates Infor ERPs and third-party enterprise systems. ION is an advanced middleware cloud platform that provides the flexibility you need to make the most complex web of enterprise systems work together on-premise, in the cloud, or both. ION’s long-term sustainability will optimize your ROI, and with ION, one application can be upgraded, replaced, or even fail without taking the entire network down.

Benefits:

  • Faster integration and upgrade times
  • Access to real-time information
  • Reduced burden on IT
  • Immediate access to business services like reporting and mobility

For older BPCS installations that don’t use ION, Crossroads RMC has the expertise to build powerful adapters to allow your specific BPCS version to communicate and exchange information with virtually any sub-system that can import/export data.
 

Infor ION Intro Video (2:11)

First2829303133353637Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last

Theme picker

Categories