BPCS/LX Tip of the Week: Multi-level Shop Order Release Due Dates

Previously, Material Requirements Planning (MRP) preferred practices meant that the component’s due date was the same as the parent’s shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The user is now able change how the due date is determined for multi-level shop orders. If the Due Date of Children parameter is set to 1=Yes, the due date of the child components is the same as the release date of the parent. If the parameter is set to 0=No, the due date is the day before the release date of the parent.

Optimize Your Manufacturing Today!

Previous Article Baan/LN Tip of the Week: How is Your Productivity?
Next Article Demand-Driven Manufacturing Metrics that Drive Action - White Paper
Print
27610 Rate this article:
5.0
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The Customer Tax Exemption Maintenance program, SYS160, allows you to specify customer declarations used by the Customer Order Entry (ORD) and Billing (BIL) applications to apply a tax rate code to specific order lines of an invoice.

With this program, Infor LX can invoice customers without value-added tax (VAT) if one of the following conditions occurs:

  • The cumulated...

Don’t laugh! I know, I know…many of our customers say that after 7-10 years they are finally settling in after the implementation! We have seen many a customer stretch out the lifespan of their ERP system to 20+ years. That sounds great for the company’s bank account, but is it good for the business?

An outdated ERP system hurts your business in many ways, not just with slow performance. The best-of-breed functionality is now 2 decades old, and obsolete technology can't leverage newer technology. Lack of integration leads to siloed data that hurts communication and your internal teams feel the pain, and your customers are noticing. Poor visibility into your operations makes it nearly impossible to achieve industry-based regulatory compliance and meet financial auditing requirements. Not to mention the sheer size of Big Data that is being collected today vs. 2 decades ago or the fact that your vendor is no longer supporting your ERP version.

Let’s scrap it all and start over!...

First3031323335373839Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

1345678910Last

Theme picker

Categories