Infor LX & BPCS Tip: MPS Planned vs. MRP Planned

What items should be MPS planned, and what items should be MRP planned?
Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor LX (ERP LX) will calculate the cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.
Previous Article Infor LN & Baan Finance Tip: MPS Planned vs. MRP Planned
Next Article What are your production orders telling you?
Print
15589 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

In order to communicate effectively as a team, everyone needs to speak the same language and operate off the same playbook. If decisions are made based on the data or the view of data that individuals are maintaining through their own spreadsheets or other data silos, then communication is negatively impacted.

Manufacturers need to review large amounts of data every day, making it difficult to keep track of key metrics within your department.

That’s where Crossroads RMC’s Analytics Dashboard solution comes in. Our Analytics Dashboard was developed to make tasks easier by putting all of the key information in one convenient location so you can view all of your crucial data in real-time. 

With powerful dashboards, you can...

Did you know that the system stores a record of every inventory transaction and makes them available for inquiries and reports? Transaction history is available for immediate inquiry by item, or by item and location in the Material Status Inquiry program. The inventory transaction record holds data such as the quantity, date, reference number, cost/value, transaction type, scheduled date, and master reference number, lot numbers, and warehouse/location information.

First3233343537394041Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

1345678910Last

Theme picker

Categories