BPCS/LX TIP OF THE DAY: MATERIAL REQUIREMENT DATES AND LEAD TIME OFFSETS IN MRP

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Previous Article Infor LN 10.4.1 Release Notes
Next Article Key Solution Strengths For Process Manufacturers
Print
38820 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Use the Invoice Level Inquiries program, ACR300D7, to perform online customer account receivable inquiries and to perform write-off transactions on open invoices. The inquiries display customer master file and credit information, open and closed invoices, debits, credits, payments, and dunning statuses. Additional detail information is available, such as original prefix and document number, customer order number, customer purchase order number, reason codes, and currency.

You can view closed items for a period specified in Transaction History System Parameters, SYS824D-01.

Open items are aged in one of five user-defined aging periods as defined in Accounts Receivable Parameters, ACR820D-01.

This program features multiple-level shop calendar maintenance. You can maintain a shop calendar at the global, facility, or work center level. Global level entries override default values found in Work Center Maintenance, CAP100D1, for any program that uses the shop calendar.

Facility overrides affect all work centers in a Facility and are exceptions to the global level. Exceptions defined at the Facility level apply to all work centers for the facility. Work Center calendar entries are the most specific. These entries apply....

First3334353638404142Last

Theme picker

Tips: LN | Baan

Table Timestamp Definitions (ttadv4136m000)

Use this session to define timestamps for Infor LN tables. A timestamp is an additional column that stores the date and time of the last change for each record.

Timestamps are utilized by features like the extraction logic of CPM Enterprise Analytics. They enable CPM to perform incremental data extractions. For example, CPM can use the timestamps to extract records that were changed during the last week in a weekly extraction process.

To Create Timestamps...

Operations: To absorb the cost of cost items into specific projects, you'll need to handle them as customized items. However, cost items cannot directly be defined as customized items. Customized items must be physical, either manufactured or purchased.

That said, it's still possible to absorb cost items into a project, although indirectly. Here's how:

  1. Set Up Ledger Account: First, create a new ledger account in session tfgld0508m000 and set the type to "PCS" (project) in the operations management integrations. This account will be used for matching and approving purchase orders for cost items.

  2. Create and Activate Projects: Ensure that the necessary projects are created and set to active status.

  3. Purchasing Cost Items...

12345678910Last

Theme picker

Categories