Baan/LN Tip of the Week: Default Order Frequency
In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.
For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.
In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.
For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.