Baan/LN Tip of the Week: Default Order Frequency

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

Previous Article BPCS/LX Tip of the Week: What is Lean Make to Order?
Next Article Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance
Print
68187 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

An ACR system parameter allows you to specify whether to measure invoice age from the date on which you create the invoice, invoice date, or the date on which the invoice is due. You can set up a separate terms code for each customer on the system to set the basic terms of payment for that customer. For example, this term could specify the number of days an invoice can be due before it is considered past due and the number of days that a discount is available. The system uses the terms code data to...

Operations are automatically backward scheduled at shop order release time. The backward scheduling algorithm starts with the shop order due date and schedules each operation based upon the standard move and queue times in the routings and the number of days the job is expected to run at standard. The system calculates and stores the operation scheduled start date. The dates may be modified by the shop order maintenance program. The number of days that a job is expected to run an operation is dependent upon the available capacity for that work center and the total hours scheduled for that operation.

The backward scheduling algorithm also considers...

First3536373840424344Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last

Theme picker

Categories