Infor LN & Baan Tip of the Week: Job Groups in LN

In a scenario where performing job A depends on the result of job B, it is hard to decide at what time job A must be scheduled, and how long job B runs. To handle dependent jobs, you can now create a job group. Use the Job Groups (ttaad5140m000) session to create a job group. A job group has a name, with the same characteristics as a job name, and a description. The Status and User of the job group are handled automatically.

After creating the job group, the jobs are added to the group, approximately in the order the jobs must be performed. The first job in the group (with the lowest Group Number) determines the handling of the whole job group, such as execution date and whether the job group is being repeated. If the job group is not repeating, the job group and all non-repeating jobs in the job group are deleted when the job group has run.

The dependencies of the jobs in the job group are also determined. A job in the job group can only depend on a job in the same job group with a lower job number.

You can use the specific options in the Job Groups (ttaad5140m000 andttams5640m000) sessions to change the status of the job group. The job group statuses have the same meaning as the status of the jobs and the same status changes are allowed.

Note: Job groups are only handled by the BSE service Job Scheduler Service.

Previous Article A/P Payment Update in LX 8.3.4
Next Article If you can't see everything that happens on your shop floor, you are at a competitive disadvantage
Print
40640 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

An ACR system parameter allows you to specify whether to measure invoice age from the date on which you create the invoice, invoice date, or the date on which the invoice is due. You can set up a separate terms code for each customer on the system to set the basic terms of payment for that customer. For example, this term could specify the number of days an invoice can be due before it is considered past due and the number of days that a discount is available. The system uses the terms code data to...

Operations are automatically backward scheduled at shop order release time. The backward scheduling algorithm starts with the shop order due date and schedules each operation based upon the standard move and queue times in the routings and the number of days the job is expected to run at standard. The system calculates and stores the operation scheduled start date. The dates may be modified by the shop order maintenance program. The number of days that a job is expected to run an operation is dependent upon the available capacity for that work center and the total hours scheduled for that operation.

The backward scheduling algorithm also considers...

First3536373840424344Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

1345678910Last

Theme picker

Categories