Baan/LN Tip of the Week: SIC Planning for MRP/MPS Planned Items

If you have a parts warehouse and prefer to use SIC for planning (re-order point) but need to use MRP/MPS planning for production, create a non-nettable warehouse for the parts warehouse and run the SIC plan against that warehouse.

When running the SIC plan, be sure to set the Order System to “MPS to MRP” for Baan IV and to “Planned to Planned” for Baan V and LN.

Using this method you keep the parts inventory out of the production planning and in the hands of the parts warehouse planner.

Previous Article Downtime & Data Loss – How Much Can You Afford?
Next Article BPCS/LX Tip of the Week: Work Center & Machine Locations
Print
54762 Rate this article:
3.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Serial Number Unique ID Generator - The new Serial Number Unique ID Generator program (INV599B3) is used to generate a unique value that groups a set of serial numbers that should be treated as part of a single, comprehensive set of inventory transactions.

Assign Unique Sequence Number - The new Assign Unique Sequence Number program (SYS046B) is used by any program that posts an inventory transaction, that is, writes an...

Use the Production Register Listing screen, JIT610D1-01, to print an edit list of the labor tickets that you added or updated. Use this report to see the data to post before you actually perform the update. After you print the edit list, you can go back to Production Reporting (JIT600) and change the data before you post the batch. The program assigns a number to each production report that you posted in JIT600. You can use JIT600 to reference the production report that you want to update. Access: Specify Post on Production Reporting, JIT600D1-01.

First4142434446484950Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last

Theme picker

Categories