Baan/LN Tip of the Week: Default Order Frequency

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

Previous Article BPCS/LX Tip of the Week: What is Lean Make to Order?
Next Article Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance
Print
68187 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

This program generates an uncosted items listing for the specified facility and cost set. You can use this report as an exception listing to identify those items that are currently maintained at zero cost or new items that require entry prior to cost rollup in Cost Set Rollup, CST500.

If a facility-specific component cost does not exist for a parent being rolled up, zero cost is rolled up for the component. When a new parent item is being rolled up for the first time, the audit report for Cost Rollup, CST500, displays a warning wherever a component cost is zero. Rolling up the parent cost again does not display a message for zero component costs.

Access: Menu CST01

First4243444547495051Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements: