Baan/LN Tip of the Week: SIC Planning for MRP/MPS Planned Items

If you have a parts warehouse and prefer to use SIC for planning (re-order point) but need to use MRP/MPS planning for production, create a non-nettable warehouse for the parts warehouse and run the SIC plan against that warehouse.

When running the SIC plan, be sure to set the Order System to “MPS to MRP” for Baan IV and to “Planned to Planned” for Baan V and LN.

Using this method you keep the parts inventory out of the production planning and in the hands of the parts warehouse planner.

Previous Article Downtime & Data Loss – How Much Can You Afford?
Next Article BPCS/LX Tip of the Week: Work Center & Machine Locations
Print
54762 Rate this article:
3.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

You know what ERP data you need to analyze your company’s production health, but sometimes it is a struggle to get that data in a format that is meaningful. Here are some reports in BPCS & Infor LX which you may find useful.

As is the case with most ERP reports, with each version progression from the earliest versions of BPCS to the latest version of Infor LX, there are improvements in selection criteria and report content. Some may require some setup and others may require some formatting if you would like to export them to Excel. Contact me if you have questions or need assistance.

BPCS & LX MANUFACTURING:

You know what ERP data you need to analyze your company’s financial health, but sometimes it is a struggle to get that data in a format that is meaningful. Here are some reports in BPCS & Infor LX which you may find useful.

As is the case with most ERP reports, with each version progression from the earliest versions of BPCS to the latest version of Infor LX, there are improvements in selection criteria and report content. Some may require some setup and others may require some formatting if you would like to export them to Excel. Contact me if you have questions or need assistance.

BPCS & LX FINANCE:

First4546474850525354Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last