Infor LN & Baan Finance Tip: MPS Planned vs. MRP Planned

What items should be MPS planned, and what items should be MRP planned…

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, your ERP will calculate the cumulative lead time (also called “the Critical Path”) for you.


Infor LN does not differentiate between the two. It is simply Enterprise Planning EP with one set of planned orders. It's possible to set up items and generate orders at plan levels, but not necessary. In theory, you could make plan level 1 similar to MPS items.

Another way of defining independent demand in LN terms is that it is demand not related to other planned items. Dependent demand comes from related planned items above in the BOM structure.

COLT still exists in the purchase and manufactured planned items. It has non-critical and critical lead time based on components set as critical. Once calculated it can be used to update the order and planning horizons of a plan item.

Relevant Sessions:

In Baan IV
Maintain Item Data tiitem0101m000
Generate MPS timps3201m000
Maintain Master Production Schedule timps3101m000
Display Planned Inventory Movements by Item timrp1510m000
Display Planned MRP Purchase Orders timrp1521m000

In Baan V

Plan Item Data cprpd1500m000
Item Master Plan cprmp2101m000
Time-Phased Overview cprrp0520m000

In Infor LN

Item – Planning cprpd1100m000
Item Master Plan cprmp2101m000 (same as Master MPS above if used)

Contact us today to learn more:  800.762.2077 | solutions@crossroadsrmc.com

Previous Article LX User Group Event: Infor Partner Spotlight | Crossroads RMC
Next Article Infor LX & BPCS Tip: MPS Planned vs. MRP Planned
Print
19589 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

What will you do when your ERP is no longer supported in 2021?

This is a confusing time for many companies with respect to their ERP system.

"Will I still be able to run my current version?"
"What happens if I want to stay on my version?"
"What options do I have?"

Crossroads RMC is here to help you sort through the confusion and get you to a place where you feel confident about your ERP future.

Let's get started with how we can help. I want Crossroads RMC to…

  • Conduct an Infor ERP Utilization Review – Should I consider moving to the latest version of LX in the cloud, or on prem? If I don’t, what are my options?
     
  • Set up an Infor ERP Demo System – I want to give my employees a chance to try out the latest version to see if it would be of benefit.
     
  • Train My Employees – I want to ensure that we’re operating based on best practices.
     
  • Integrate My ERP to External Systems – My company uses separate systems that don’t talk to one another and that is really inefficient.
     
  • Brainstorm With Me – I’m not sure what to do. I need to talk through some scenarios with someone who has been there, done that.
     
  • Support My Users – I’m short-staffed. I may upgrade, or I may stay where I’m at. Either way, I could use someone to handle our ERP issues. Please help!

Contact us at 800.762.2077 or click here to request a free phone consultation and we'll get you back on track.

Did you know that you can clear production history?

JIT900 - Production History Purge

To clear field values from Production History Inquiry (JIT300). Run monthly as Day End Run and Month End Run which clears M-T-D fields.  There is an option to clear the average per hour and maximum per hour fields. This program can be run as often as you wish.

First4647484951535455Last

Theme picker

Tips: LN | Baan

Table Timestamp Definitions (ttadv4136m000)

Use this session to define timestamps for Infor LN tables. A timestamp is an additional column that stores the date and time of the last change for each record.

Timestamps are utilized by features like the extraction logic of CPM Enterprise Analytics. They enable CPM to perform incremental data extractions. For example, CPM can use the timestamps to extract records that were changed during the last week in a weekly extraction process.

To Create Timestamps...

Operations: To absorb the cost of cost items into specific projects, you'll need to handle them as customized items. However, cost items cannot directly be defined as customized items. Customized items must be physical, either manufactured or purchased.

That said, it's still possible to absorb cost items into a project, although indirectly. Here's how:

  1. Set Up Ledger Account: First, create a new ledger account in session tfgld0508m000 and set the type to "PCS" (project) in the operations management integrations. This account will be used for matching and approving purchase orders for cost items.

  2. Create and Activate Projects: Ensure that the necessary projects are created and set to active status.

  3. Purchasing Cost Items...

12345678910Last

Theme picker

Categories