Infor LX & BPCS Tip: MPS Planned vs. MRP Planned

What items should be MPS planned, and what items should be MRP planned?
Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor LX (ERP LX) will calculate the cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.
Previous Article Infor LN & Baan Finance Tip: MPS Planned vs. MRP Planned
Next Article What are your production orders telling you?
Print
15734 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

What will you do when your ERP is no longer supported in 2021?

This is a confusing time for many companies with respect to their ERP system.

"Will I still be able to run my current version?"
"What happens if I want to stay on my version?"
"What options do I have?"

Crossroads RMC is here to help you sort through the confusion and get you to a place where you feel confident about your ERP future.

Let's get started with how we can help. I want Crossroads RMC to…

  • Conduct an Infor ERP Utilization Review – Should I consider moving to the latest version of LX in the cloud, or on prem? If I don’t, what are my options?
     
  • Set up an Infor ERP Demo System – I want to give my employees a chance to try out the latest version to see if it would be of benefit.
     
  • Train My Employees – I want to ensure that we’re operating based on best practices.
     
  • Integrate My ERP to External Systems – My company uses separate systems that don’t talk to one another and that is really inefficient.
     
  • Brainstorm With Me – I’m not sure what to do. I need to talk through some scenarios with someone who has been there, done that.
     
  • Support My Users – I’m short-staffed. I may upgrade, or I may stay where I’m at. Either way, I could use someone to handle our ERP issues. Please help!

Contact us at 800.762.2077 or click here to request a free phone consultation and we'll get you back on track.

Did you know that you can clear production history?

JIT900 - Production History Purge

To clear field values from Production History Inquiry (JIT300). Run monthly as Day End Run and Month End Run which clears M-T-D fields.  There is an option to clear the average per hour and maximum per hour fields. This program can be run as often as you wish.

First5051525355575859Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last

Theme picker

Categories