Infor LN & Baan OPERATIONS Tip: MPS Planned vs. MRP Planned

When deciding what items should be MPS (Master Production Schedule) planned and what items should be MRP (Material Requirements Planning) planned, it's crucial to understand the nature of the items and their demand sources. Here's a breakdown:

  • Master Scheduled Items:

    • Master Scheduled Items are typically finished goods or service items.
    • These items receive their requirements from both Independent and Dependent demand sources.
       
  • Independent Demand:

    • Independent demand cannot be calculated from higher-level demand in the product structure.
    • It is driven by forecasts or actual customer orders, primarily applicable to Finished Goods or Service parts sold to customers.
       
  • Dependent Demand:

    • Dependent demand is derived from higher-level demand in the product structure.
    • It includes components, raw materials, and sub-assemblies.
    • Dependent demand items are not typically part of Master Production Scheduling (MPS).
       
  • Service Parts:

    • Service parts can have both independent demand from forecasts or customer orders and dependent demand from higher-level demand if they are used in sub-assemblies or other products.
       
  • Cumulative Lead Time:

    • Cumulative Lead Time is a concept used in MPS.
    • It combines the fixed lead time and variable lead time required to produce a product.
    • It represents the longest path through a Bill-of-Materials (BOM).
    • Your ERP system will calculate the cumulative lead time (Critical Path) based on MPS setup options.
       
  • Infor LN Approach:

    • Infor LN does not differentiate between MPS and MRP planning.
    • It uses Enterprise Planning (EP) with one set of planned orders.
    • While you can set up items and generate orders at plan levels, it's not always necessary.
    • In theory, you could treat plan level 1 similar to MPS items.
       
  • Defining Independent Demand in LN:

    • In LN terms, independent demand is demand not related to other planned items.
    • Dependent demand comes from related planned items higher up in the BOM structure.
       
  • COLT (Cumulative Order Lead Time):

    • COLT exists in the purchase and manufactured planned items.
    • It considers non-critical and critical lead times based on components marked as critical.
    • Once calculated, COLT can be used to update the order and planning horizons of a planned item.

Relevant Sessions:

In Baan IV:

  • Maintain Item Data (tiitm0101m000)
  • Generate MPS (timps3201m000)
  • Maintain Master Production Schedule (timps3101m000)
  • Display Planned Inventory Movements by Item (timrp1510m000)
  • Display Planned MRP Purchase Orders (timrp1521m000)

In Baan V:

  • Plan Item Data (cprpd1500m000)
  • Item Master Plan (cprmp2101m000)
  • Time-Phased Overview (cprrp0520m000)

In Infor LN:

  • Item – Planning (cprpd1100m000)
  • Item Master Plan (cprmp2101m000) - Same as Master MPS if used


For more information and assistance, you can contact Crossroads RMC at 800.762.2077 or via email at solutions@crossroadsrmc.com.

Previous Article Infor LN & Baan TECHNOLOGY Tip: Are you running the latest Infor components?
Next Article Infor LX / BPCS Tips & Tricks for EXECUTIVES
Print
17640 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Clients who want to process more than one customer order line, one item, or one shop order are now able to continue processing without having to leave the Multi-Level Backflush screen. After entering data for a specific category, users are now able to use the F18=Accept & Continue function key that allows users to start and complete an action and remain on the MultiLevel Backflush screen, LMP600D1, to perform the next action. Previously, users were sent back out to the SYS500-06 screen after processing using single customer order line, shop order, or item.

This enhancement includes these programs or areas:

  • Lean Production Back-flush Selection Panel, LMP600D  
  • Lean Production Back-flush Selection Panel, LMP600FM
  • Lean Production Back-flush Selection Panel, LMP600HT

EGLi users who maintain journal entries in a Microsoft Excel spreadsheet can use this utility to upload journal entries to EGLi. The Journal Upload installation program adds an Add-Ins tab to Microsoft Excel. This tab includes options to connect to the server where EGLi is installed and to open a spreadsheet template to use for manual journal entry. When the spreadsheet is complete, the Add-Ins tab is used to upload the spreadsheet.

To install Journal Upload:

  1.  The Power-Link Installation page has links to the Client installation programs and a link to download and install the Journal Upload utility. To access this page, use this link with your own values for system and NetLinkport: http://system:NetLinkport/Installs/ClientInstall/Install.html  where system is the server where IDF is installed and NetLinkport is the Net-Link port, typically 36001
     
  2. On the Power-Link Installation page, click the link provided to download and install EGLi Journal Upload.
     
  3. Follow the screen prompts to complete the installation on your PC.
     
  4. To verify the installation, open an Excel spreadsheet. Confirm that the Add-Ins tab is on the spreadsheet. 


See the Infor Enterprise General Ledger for System i Journal Upload Installation and Infor LX Configuration Guide.

First5253545557596061Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements: