Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Baan/LN Tip of the Week: Project Templates

Project templates are useful because you can specify all of the information that you would normally want to include when creating a new project such as project structure, budget and so on.

In Baan IV/V, project templates do not exist, but you can set up a project template by creating a regular project, and setting the status to simulated or free. This is done so that the project does not create plans. Under this scenario, you can easily copy one project to another.

In LN, when you create a new project, a template can be used as the starting point. This is similar to copying a normal project, but unlike normal projects, no costs or revenues can be posted on a template.

Optimize Your Manufacturing Today!

 

Previous Article Infor LX and Crossroads MES Selected by Blonder Tongue
Next Article BPCS/LX Tip of the Week: Actual Versus Standard
Print
36799 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

EGLi provides Infor LX Configurable Enterprise Accounting (CEA) functionality including Advanced Transaction Processing (ATP), a configurable ledger, and batch transaction processing in the IDF architecture.

EGLi is a complete replacement for CEA. Infor LX applications integrate with EGLi, and subsystem transactions generated in Infor LX are used to create journal entries in EGLi. The Infor LX integration system parameters allow you to specify whether CEA or EGLi is your primary financial product.

We recommend that you select CEA while you test the integration. The primary financial product flag and the CEA migration programs are designed to assist existing CEA clients with their implementation of EGLi. Journals are produced in both GL systems so you can verify that the data in both GL systems are the same. This integration includes migration programs that copy your existing CEA files to corresponding EGLi files. After you run the migration programs, EGLi should be configured and ready to use. If you are already running IDF via Ming.le or SiW, before you install EGLi, you will need to see the Ming.le integration guide for instructions on how to export EGLi tasks from IDF to SiW/Ming.le.

Learn More > Infor LX Integration Guide for Enterprise General Ledger

  • Control Date Lead Times – LX provides five separate Control Date Lead Time fields so you can specify additional lead time values for Shop Orders, Purchase Orders and Planned and Firm Planned orders. Each Control Lead Time Date represents additional time (days) required at each step in the process that needs more time (Quarantine, Stabilize), that is to say, when a component is due, and when it can be used. (working with an aerospace  precision bearing manufacturer, I had to account for the QA requirement that no measurements could be taken until the parts had been “soaked” (stored) in an atmospheric controlled environment (72 degrees, and controlled humidity) for 24 hours. This requirement added one full day of lead time between each machining operation) The MPS/MRP Generation program, as well as programs that Shop Order Material Allocation records use the five control date lead times to adjust component required dates to function in the same way as the BOM Offset Lead Time.
     
  • All programs that create MRP Planned Orders, MRP Firm Planned Orders, Shop Orders, and Purchase Orders call the Control Date Calculation program (MRP515B) to establish all five control dates. A Control Lead Time Date is used to adjust the component Required Dates data in the Material Requirements file (KMR), based on planned orders for a parent, and the FMA Required Dates data, based on shop order release dates for a parent.
First5859606163656667Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last

Theme picker

Categories