BPCS/LX TIP OF THE DAY: MATERIAL REQUIREMENT DATES AND LEAD TIME OFFSETS IN MRP

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Previous Article Infor LN 10.4.1 Release Notes
Next Article Key Solution Strengths For Process Manufacturers
Print
38746 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

This enhancement simplifies access to LX programs that are available through System i Manager (SiM), as well as Workflow for System I (WFi). This provides an easy way to promote common WFi business processes from one LX environment (for example, test or environment) to another LX environment (for example, production). 

LX also provides a set of four-character task codes that can be used within SiM, System i Workspace (SiW), and WFi, for default programs in LX. These predefined LX task codes begin with 0,1,2,3, or 4. Users can specify task codes for their custom programs that are flagged as valid menu options in LX, but these task codes cannot begin with 0,1,2,3, or 4. Users can specify the task codes in Infor LX Object Master Maintenance, SYS625D. This enhancement provides simplified access to LX programs that are flagged as valid menu options in System i Manager and Workflow for System i environments. In SYS625D, The user can also specify task codes in SYS625D for customized programs that are flagged as valid menu options.

Users are no longer limited to backing up or saving files to a tape or diskette.They can now use a Save File (SAVF) to save data and objects. LX programs that perform saves and/or backups were modernized to add a new SAVF option.  

There were numerous places in LX where users are prompted to save a file or library. These screens have options for tape or diskette. Diskette refers to the old 8” diskettes used on System/38. These devices are outdated and virtually obsolete. The current means of saving objects on the IBM i, is through the use of a Save File (SAVF). This compresses the data into a single object that can be saved and is easily transferred between systems.

These objects were modified and/or created for this enhancement:

  • Backup Simulation (FOR630C, FOR630D, FOR630FM, FOR640HT, and FOR630HT)
  • Month End Close (INV903D, INV903FM, INV901C, and INV903HT)
  • Purge YTH/Restore Archived Lots (INV912C, INV912D, INV912DHT, and INV912FM)
  • Purge and Save ITH records (INV932C, INV932D, INV932FM, and INV932HT)
  • Labor Ticket Save (SFC905D, SFC905FM, SFC901C, and SFC905HT)
  • Backup Infor LX Files (SYS700C, SYS700D, SYS700FM, and SYS700HT)
  • Backup Infor LX Programs (SYS710C, SYS710D, SYS710FM, and SYS710HT)
  • Backup Infor LX Source (SYS740C, SYS740D, SYS740FM, and SYS740HT)
  • Save File Name Selection (SYS912D, SYS912FM, and SYS912HT)


Benefit

Use the Backup Simulation to copy a simulation file to a SAVF or tape. Users may want to do this to transfer simulation data from one system to another, from site to site, or to save the data before permanently deleting it from the system.

First6566676870727374Last

Theme picker

Tips: LN | Baan

Table Timestamp Definitions (ttadv4136m000)

Use this session to define timestamps for Infor LN tables. A timestamp is an additional column that stores the date and time of the last change for each record.

Timestamps are utilized by features like the extraction logic of CPM Enterprise Analytics. They enable CPM to perform incremental data extractions. For example, CPM can use the timestamps to extract records that were changed during the last week in a weekly extraction process.

To Create Timestamps...

Operations: To absorb the cost of cost items into specific projects, you'll need to handle them as customized items. However, cost items cannot directly be defined as customized items. Customized items must be physical, either manufactured or purchased.

That said, it's still possible to absorb cost items into a project, although indirectly. Here's how:

  1. Set Up Ledger Account: First, create a new ledger account in session tfgld0508m000 and set the type to "PCS" (project) in the operations management integrations. This account will be used for matching and approving purchase orders for cost items.

  2. Create and Activate Projects: Ensure that the necessary projects are created and set to active status.

  3. Purchasing Cost Items...

12345678910Last

Theme picker

Categories