Infor LN & Baan Tip: Outbound Order Lines

When the originating order or order line of an outbound order line is canceled or changed, this affects the outbound order line and may impact the related outbound advice, shipments, or shipment lines.

For most order origins, warehousing order-type parameters determine whether these actions are allowed:

  1. Update the outbound order line if the originating order is changed.
  2. Cancel the originating order line and the outbound order line.
  3. Delete the canceled outbound order line.

Updating Outbound Order Lines

  • Allowed: Changes made to the originating order are updated to the outbound order line. Related outbound advice and picking lists, if present, are deleted.
  • Not Allowed: A message is displayed, and input is blocked when trying to change the originating order line.

Canceling Outbound Order Lines

  • Allowed: The outbound order line is deleted or set to Canceled when the originating order line is canceled.
    • When a canceled outbound order line is deleted, related outbound advice and picking lists are also deleted.
    • Outbound order lines originating from manual order origins cannot be deleted when canceled.
  • Not Allowed: You cannot cancel the originating order line or the outbound order line. A message is displayed when attempting to cancel the originating order line.

Processing Canceled Outbound Order Lines

  • To process an outbound order line set to Canceled, the outbound order line must be set to Shipped.
  • The status of the outbound order line determines whether all steps of the outbound and shipment procedures must be completed.
  • When a canceled outbound order line is set to Shipped, the shipped quantity is automatically set to 0.
  • A transfer order can be created to return the not-shipped goods to inventory.

Preventing Shipment When Canceling is Not Allowed

  • Complete the outbound and shipment procedures to prevent goods from being shipped.
  • When confirming the shipment line, set the shipped quantities to 0 and create a transfer order to return the not-shipped goods to inventory.

Previous Article inPower 2024 - Join Gold Sponsor Crossroads RMC
Next Article Reskilling and Upskilling Your Staff – Why You Shouldn’t Ignore This
Print
6112 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

This feature provides the ability to enter information in the shelf life days and retest days fields for non-QMS lot controlled items, even when the QMS product is installed. The purpose of this enhancement is to allow the user to enter information for non-QMS lot controlled items even when QMS is activated in Parameters Generation, SYS800D. In previous versions, when QMS was activated, the Shelf Life Days and Retest Days fields in Facility Planning Maintenance (MRP140) and Item Master Maintenance (INV100) were not maintainable for non-QMS lot controlled items. The user is now able to change non-QMS lot controlled items even when a QMS product is installed.

The Facility Period Close process, as introduced in Infor LX 8.3.4, was designed to function interactively. 

The expectation was that clients with a continuous or 24-hour worldwide operation in multiple facilities would submit the Period End Close jobs for each facility as daily operations ceased or shifts ended for each facility. This process was designed to function interactively so that validations of users performing transactions that conflicted with period end processing, and resulting messages, were immediately sent to the period end user. 

This enhancement provides a batch mode for the Facility Period Close (INV930) process and allows the Update IIM Inventory from IWI (INV931) process to be submitted from the INV930B program. The enhancement also provides a batch mode for the INV931 process. For example, a user has a 24-hour operation in facilities around the world, but a centralized IT operation. With this enhancement the user can submit the individual facilities to be closed to a batch process that can be managed by a scheduler, automatically releasing each facility to be closed at a predetermined time.

First6667686971737475Last

Theme picker

Tips: LN | Baan

Table Timestamp Definitions (ttadv4136m000)

Use this session to define timestamps for Infor LN tables. A timestamp is an additional column that stores the date and time of the last change for each record.

Timestamps are utilized by features like the extraction logic of CPM Enterprise Analytics. They enable CPM to perform incremental data extractions. For example, CPM can use the timestamps to extract records that were changed during the last week in a weekly extraction process.

To Create Timestamps...

Operations: To absorb the cost of cost items into specific projects, you'll need to handle them as customized items. However, cost items cannot directly be defined as customized items. Customized items must be physical, either manufactured or purchased.

That said, it's still possible to absorb cost items into a project, although indirectly. Here's how:

  1. Set Up Ledger Account: First, create a new ledger account in session tfgld0508m000 and set the type to "PCS" (project) in the operations management integrations. This account will be used for matching and approving purchase orders for cost items.

  2. Create and Activate Projects: Ensure that the necessary projects are created and set to active status.

  3. Purchasing Cost Items...