BPCS/LX TIP OF THE DAY: MATERIAL REQUIREMENT DATES AND LEAD TIME OFFSETS IN MRP

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Previous Article Infor LN 10.4.1 Release Notes
Next Article Key Solution Strengths For Process Manufacturers
Print
38746 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

This feature provides the ability to enter information in the shelf life days and retest days fields for non-QMS lot controlled items, even when the QMS product is installed. The purpose of this enhancement is to allow the user to enter information for non-QMS lot controlled items even when QMS is activated in Parameters Generation, SYS800D. In previous versions, when QMS was activated, the Shelf Life Days and Retest Days fields in Facility Planning Maintenance (MRP140) and Item Master Maintenance (INV100) were not maintainable for non-QMS lot controlled items. The user is now able to change non-QMS lot controlled items even when a QMS product is installed.

The Facility Period Close process, as introduced in Infor LX 8.3.4, was designed to function interactively. 

The expectation was that clients with a continuous or 24-hour worldwide operation in multiple facilities would submit the Period End Close jobs for each facility as daily operations ceased or shifts ended for each facility. This process was designed to function interactively so that validations of users performing transactions that conflicted with period end processing, and resulting messages, were immediately sent to the period end user. 

This enhancement provides a batch mode for the Facility Period Close (INV930) process and allows the Update IIM Inventory from IWI (INV931) process to be submitted from the INV930B program. The enhancement also provides a batch mode for the INV931 process. For example, a user has a 24-hour operation in facilities around the world, but a centralized IT operation. With this enhancement the user can submit the individual facilities to be closed to a batch process that can be managed by a scheduler, automatically releasing each facility to be closed at a predetermined time.

First6667686971737475Last

Theme picker

Tips: LN | Baan

Table Timestamp Definitions (ttadv4136m000)

Use this session to define timestamps for Infor LN tables. A timestamp is an additional column that stores the date and time of the last change for each record.

Timestamps are utilized by features like the extraction logic of CPM Enterprise Analytics. They enable CPM to perform incremental data extractions. For example, CPM can use the timestamps to extract records that were changed during the last week in a weekly extraction process.

To Create Timestamps...

Operations: To absorb the cost of cost items into specific projects, you'll need to handle them as customized items. However, cost items cannot directly be defined as customized items. Customized items must be physical, either manufactured or purchased.

That said, it's still possible to absorb cost items into a project, although indirectly. Here's how:

  1. Set Up Ledger Account: First, create a new ledger account in session tfgld0508m000 and set the type to "PCS" (project) in the operations management integrations. This account will be used for matching and approving purchase orders for cost items.

  2. Create and Activate Projects: Ensure that the necessary projects are created and set to active status.

  3. Purchasing Cost Items...

12345678910Last

Theme picker

Categories