Infor LX & BPCS Tip of the Week: MPS vs. MRP

What items should be MPS planned, and what items should be MRP planned…

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor/ERP LX will calculate cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.
Previous Article You’ve got a handle on your inventory requirements, right? Are you confident you can handle a rush order, or ten rush orders?
Next Article Consulting News: How do I identify the processes that impact my ERP upgrade?
Print
40649 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

This feature provides the ability to enter information in the shelf life days and retest days fields for non-QMS lot controlled items, even when the QMS product is installed. The purpose of this enhancement is to allow the user to enter information for non-QMS lot controlled items even when QMS is activated in Parameters Generation, SYS800D. In previous versions, when QMS was activated, the Shelf Life Days and Retest Days fields in Facility Planning Maintenance (MRP140) and Item Master Maintenance (INV100) were not maintainable for non-QMS lot controlled items. The user is now able to change non-QMS lot controlled items even when a QMS product is installed.

The Facility Period Close process, as introduced in Infor LX 8.3.4, was designed to function interactively. 

The expectation was that clients with a continuous or 24-hour worldwide operation in multiple facilities would submit the Period End Close jobs for each facility as daily operations ceased or shifts ended for each facility. This process was designed to function interactively so that validations of users performing transactions that conflicted with period end processing, and resulting messages, were immediately sent to the period end user. 

This enhancement provides a batch mode for the Facility Period Close (INV930) process and allows the Update IIM Inventory from IWI (INV931) process to be submitted from the INV930B program. The enhancement also provides a batch mode for the INV931 process. For example, a user has a 24-hour operation in facilities around the world, but a centralized IT operation. With this enhancement the user can submit the individual facilities to be closed to a batch process that can be managed by a scheduler, automatically releasing each facility to be closed at a predetermined time.

First7071727375777879Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last

Theme picker

Categories