Infor LN & Baan OPERATIONS Tip: MPS Planned vs. MRP Planned

When deciding what items should be MPS (Master Production Schedule) planned and what items should be MRP (Material Requirements Planning) planned, it's crucial to understand the nature of the items and their demand sources. Here's a breakdown:

  • Master Scheduled Items:

    • Master Scheduled Items are typically finished goods or service items.
    • These items receive their requirements from both Independent and Dependent demand sources.
       
  • Independent Demand:

    • Independent demand cannot be calculated from higher-level demand in the product structure.
    • It is driven by forecasts or actual customer orders, primarily applicable to Finished Goods or Service parts sold to customers.
       
  • Dependent Demand:

    • Dependent demand is derived from higher-level demand in the product structure.
    • It includes components, raw materials, and sub-assemblies.
    • Dependent demand items are not typically part of Master Production Scheduling (MPS).
       
  • Service Parts:

    • Service parts can have both independent demand from forecasts or customer orders and dependent demand from higher-level demand if they are used in sub-assemblies or other products.
       
  • Cumulative Lead Time:

    • Cumulative Lead Time is a concept used in MPS.
    • It combines the fixed lead time and variable lead time required to produce a product.
    • It represents the longest path through a Bill-of-Materials (BOM).
    • Your ERP system will calculate the cumulative lead time (Critical Path) based on MPS setup options.
       
  • Infor LN Approach:

    • Infor LN does not differentiate between MPS and MRP planning.
    • It uses Enterprise Planning (EP) with one set of planned orders.
    • While you can set up items and generate orders at plan levels, it's not always necessary.
    • In theory, you could treat plan level 1 similar to MPS items.
       
  • Defining Independent Demand in LN:

    • In LN terms, independent demand is demand not related to other planned items.
    • Dependent demand comes from related planned items higher up in the BOM structure.
       
  • COLT (Cumulative Order Lead Time):

    • COLT exists in the purchase and manufactured planned items.
    • It considers non-critical and critical lead times based on components marked as critical.
    • Once calculated, COLT can be used to update the order and planning horizons of a planned item.

Relevant Sessions:

In Baan IV:

  • Maintain Item Data (tiitm0101m000)
  • Generate MPS (timps3201m000)
  • Maintain Master Production Schedule (timps3101m000)
  • Display Planned Inventory Movements by Item (timrp1510m000)
  • Display Planned MRP Purchase Orders (timrp1521m000)

In Baan V:

  • Plan Item Data (cprpd1500m000)
  • Item Master Plan (cprmp2101m000)
  • Time-Phased Overview (cprrp0520m000)

In Infor LN:

  • Item – Planning (cprpd1100m000)
  • Item Master Plan (cprmp2101m000) - Same as Master MPS if used


For more information and assistance, you can contact Crossroads RMC at 800.762.2077 or via email at solutions@crossroadsrmc.com.

Previous Article Infor LN & Baan TECHNOLOGY Tip: Are you running the latest Infor components?
Next Article Infor LX / BPCS Tips & Tricks for EXECUTIVES
Print
17605 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

From John O'Kelly's article on Manufacturing.net:

"Regardless of industry, efficiency gains and increased speed provide a competitive edge. The ever-increasing competition in the manufacturing world makes it necessary to find new, efficient ways to speed up the process while remaining accurate and productive. While flying robots and miracle technologies may promise to reshape the industry, we still have a way to go until full automation, and thus the most important asset on the manufacturing floor in 2019 will remain its people.

In 2019, the focus will undoubtably be increasing efficiencies, and this can be achieved through investing in employees, equipping them with the proper techniques and tools. An invested labor force will limit mistakes on the manufacturing floor and improve throughput at every level of the process."

Here are a few best practices to increase efficiency on the manufacturing floor in 2019:

  1. Invest in your labor force
  2. Prioritize quality assurance
  3. Improve labeling errors

You can read the full article with detailed descriptions at: https://blog.safe.com/

Optimize Your Manufacturing Today!

BPCS & LX Tip of the Week: Get Real!

You’ve got an ERP system, so everything should be real-time and everyone should have access to information in real-time, right? RIGHT?!

Why not? Why are there spreadsheets, and separate Access databases off to the side?

Data loses value over time, so why not give everyone up to date, accurate information all the time? Take a look at those silos of information and see how you can eliminate them. Your business will benefit greatly as a result.

Optimize Your Manufacturing Today!

First7172737476787980Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

1345678910Last

Theme picker

Categories