Infor LX & BPCS Manufacturing Tip: Shop Calendar Maintenance – SFC140D1

Shop calendar maintenance, SFC140D1 This program features multiple-level shop calendar maintenance. You can maintain a shop calendar at the global, facility, or work center level. Global level entries override default values found in Work Center Maintenance, CAP100D1, for any program that uses the shop calendar.

Facility overrides affect all work centers in a Facility and are exceptions to the global level. Exceptions defined at the Facility level apply to all work centers for the facility. Work Center calendar entries are the most specific. These entries apply to a single work center and override any Global or Facility conditions.

If you have deleted a work center in Work Center Maintenance, CAP100D1, you cannot delete its shop calendar. The system treats the work center shop calendar like a global calendar for that year. If you try to delete it, you will delete the global shop calendar for that year.

Range processing provides daily or weekly maintenance of all overrides for a period of up to one year with a single command.

The following explains how Infor LX uses calendars for manufactured and purchased parts planning:

  • Infor LX treats purchased and manufactured parts in the same way.
  • Infor LX does not use the work center calendar.
  • In facility planning, Infor LX uses the facility calendar.
  • If the global calendar has additional days blocked out relative to the facility calendar, MRP/MPS plans consider both the facility and global days-off.


In all cases, the system uses the item master/CIC lead time parameter to determine the release date for the planned order regarding the due date from the forecast or parent demand. The system considers days blocked out in the facility and global calendars when it determines the planned order release date.

Example: Assume the entire system (Global) has a specific date set as a regular workday. If one particular Facility recognizes this day as a holiday, no hours are available on work centers within that facility. If conditions at one work center are an exception to this holiday, that work center can be maintained with its own set of conditions.

Simulation Mode

The Shop Calendar Selection/Maintenance Simulation program, MRP747B, uses the Shop Calendar Maintenance programs, SFC140D, in a simulation mode. The MRP program allows you to maintain shop calendar information to simulate capacity planning and to view the results before you use the data in live capacity planning.

When you run MPS by facility, you cannot maintain global calendars. This safeguard prevents a user from unintentionally overwriting the live global calendar if the user runs Copy to Live, MRP770D.

Access: Menu SFC

Previous Article Infor LX & BPCS Materials Tip: Over-Receipts
Next Article Infor LN & Baan Manufacturing Tip: Performance Problems in Generate Order Planning (cprrp1210m000)
Print
19278 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

For many businesses, a high-powered ERP can streamline processes, increase efficiency, and strengthen the bottom line—at least in theory. In reality, some companies miss out on the opportunity to achieve greater ROI by overlooking a few fundamental truths about ERPs.

1. Implementation takes longer than usually anticipated.

2. Company buy-in and sufficient training can predict success.

3. Implementing the full range of features can make the difference between success and failure.

Can your ERP move with you into your next growth phase? Can it scale and flex as your business expands? Is your business making the most of your investment?

Read Full Article

Optimize Your Manufacturing Today!

The Notes Maintenance feature is made up note programs that are accessible from a central location. The Note Text Maintenance (SYS555), Note Type Maintenance (SYS553) and Multi Language Notes Maintenance (SYS556) programs are all available as menu options.

Instead of having to go into separate programs to maintain note settings, the user can set up print options, specify user documents and customize user security levels for specific notes.

The Notes Maintenance feature provides a way to create, revise, delete, and copy note text that are categorized by note types. The print options in Notes Maintenance permit a user to define documents for which the note is intended. This includes base LX documents and custom documents. 

Finally, the notes program provides a way to define notes by assigning document types. For example, a document type can be created named “Invoice.” A note can then be defined to print on all invoice programs without requiring individual entry.

Optimize Your Manufacturing Today!

First7475767779818283Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements: