Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Infor LN & Baan Finance Tip: MPS Planned vs. MRP Planned

What items should be MPS planned, and what items should be MRP planned…

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, your ERP will calculate the cumulative lead time (also called “the Critical Path”) for you.


Infor LN does not differentiate between the two. It is simply Enterprise Planning EP with one set of planned orders. It's possible to set up items and generate orders at plan levels, but not necessary. In theory, you could make plan level 1 similar to MPS items.

Another way of defining independent demand in LN terms is that it is demand not related to other planned items. Dependent demand comes from related planned items above in the BOM structure.

COLT still exists in the purchase and manufactured planned items. It has non-critical and critical lead time based on components set as critical. Once calculated it can be used to update the order and planning horizons of a plan item.

Relevant Sessions:

In Baan IV
Maintain Item Data tiitem0101m000
Generate MPS timps3201m000
Maintain Master Production Schedule timps3101m000
Display Planned Inventory Movements by Item timrp1510m000
Display Planned MRP Purchase Orders timrp1521m000

In Baan V

Plan Item Data cprpd1500m000
Item Master Plan cprmp2101m000
Time-Phased Overview cprrp0520m000

In Infor LN

Item – Planning cprpd1100m000
Item Master Plan cprmp2101m000 (same as Master MPS above if used)

Contact us today to learn more:  800.762.2077 | solutions@crossroadsrmc.com

Previous Article LX User Group Event: Infor Partner Spotlight | Crossroads RMC
Next Article Infor LX & BPCS Tip: MPS Planned vs. MRP Planned
Print
21611 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

The Enterprise Item application in the Infor Development Framework for Infor LX supports display of all information relevant to an item. This includes numerous aspects of Inventory, including facility, warehouse, location, lot, and container data.

With the Enterprise Items application, you can customize the data displayed to include more or less data than is currently displayed using the standard Infor LX programs. You can access this information through a single point of entry, so there is no need to switch from one program to another to see all the data you require. This ability to customize will help streamline your decisions by allowing you to display information that is specific to your needs.

The various Enterprise Item application cards provide listings, maintenance type information, and current information that you could previously only access by running multiple standard Infor LX programs, such as Material Status Inquiry (INV300), Bill of Material Inquiry (BOM300), and Routing Inquiry (SFC100).

Optimize Your Manufacturing Today!

This enhancement to the Purchase Receipts screens; optionally shown with the quantity and weight fields populated with the open value on the purchase order. Previously the user had to manually enter the quantity received or, for a dynamic weight and measure items, the weight received for each line on the purchase order. Now the screens are populated with the open value and if the open value is the same as the value received, the user can simply accept the line.

The Receive All field on the PUR550D1-01 screen determines whether the receipt lines are populated with the open value. A system parameter controls the Receive All default value but the default value can be overridden. If the user specifies 1=Yes in the Receive All field then the PUR550D2-02 screen displays the open quantity or weight for each line. The user can accept the open value for each line. 

Optimize Your Manufacturing Today!

First7576777880828384Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last

Theme picker

Categories