Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Tip of the Week: 8 Ways to Improve Production Efficiency in Your Manufacturing Plant

No matter how large or small your manufacturing plant is, efficiency and productivity relative to your capital investment are the keys to maintaining your competitive edge. Wasting time and money is not something anyone wants to do, but manufacturers need to be especially mindful of both and actively work to address any issues that lead to productivity or financial loss.

Source: https://www.onupkeep.com/blog/improve-production-efficiency/

Previous Article Infor LN & Baan Tip of the Week: Dynamic Assembly Control BOM (LN 10.7)
Next Article Infor LX & BPCS Tip of the Week: Fast Line Entry
Print
64092 Rate this article:
5.0
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Here are 5 ways you can motivate your employees to give their best every day:

1. Train Your Employees

2. Give Your Employees the Right Tools

3. Automate Processes

4. Give Your Employees Real-Time Feedback

5. Provide Incentives to Do More

Optimize Your Manufacturing Today!

Previously, Material Requirements Planning (MRP) preferred practices meant that the component’s due date was the same as the parent’s shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The user is now able change how the due date is determined for multi-level shop orders. If the Due Date of Children parameter is set to 1=Yes, the due date of the child components is the same as the release date of the parent. If the parameter is set to 0=No, the due date is the day before the release date of the parent.

Optimize Your Manufacturing Today!

First7980818284868788Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last

Theme picker

Categories