Infor LN & Baan Tip of the Week: Dynamic Assembly Control BOM (LN 10.7)

In previous releases of LN, the Assembly Control Bill of Material (BOM) offered limited flexibility. For each end item configuration, users were required to create unique Engineering Modules, which are used to determine the assembly parts that are consumed in a specific Line Station during a specific operation.

If LN is integrated with Design Studio, previously called Infor CPQ, BOM structures can be maintained in Design Studio for Assembly Control. These structures can include non-configurable parts that are directly linked to configurable items. When communicating these structures to LN using the Assembly Control, Product Variant Structure (tiapl3510m000) session, the structures were rejected because non-configurable parts were not supported by the session logic.

In this release, BOM structures that include non-configurable parts can now be accepted in LN. Consequently, if LN is integrated with Design Studio, it is no longer required to use the Engineering Module. Using the Engineering Module has become optional.

Previous Article Infor LX & BPCS Tip of the Week: Multi-Level Backflush (LX 8.4)
Next Article Tip of the Week: 8 Ways to Improve Production Efficiency in Your Manufacturing Plant
Print
53018 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Some items in the manufacturing process may require a lot number. A quick and easy way to release the Shop Orders with lot numbers is by using the Multi-Level Shop Order Release.

Simply select the end item from the selection screen and use action 10 for the multi-level order release. At the bottom of the release screen is the field “Pre-Assign a Lot Number to Shop Orders”. Select 1 for the pre-assigned lot number assignment option.

This option will use the pre-assigned lot number on the shop order, if the lot number exists. If the lot number does not exist, the system will automatically create a lot number and assign it to the shop order for all items that are lot-controlled.

Optimize Your Manufacturing Today!

Electronic Signature Controls have been expanded to include additional programs, files and fields.  

When manufacturing work centers are updated through Work Center Maintenance (CAP100), the system can now require Electronic Signature processing to complete the process. This enhancement allows for broader Electronic Signature controls.

Optimize Your Manufacturing Today!

First8182838486888990Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

1345678910Last