BPCS/LX Tip of the Week: Shop Order Status

You can see the status of the Shop Order when using SFC300 Shop Order Inquiry. You want to be sure that your shop orders are at the correct status in order to report against them.

The following are the shop order status codes:

04 = The Shop order has been entered.

05 = The Shop order has been released and printed.

14 = The Shop order has been released, but not printed. If a shop order is at this status, you have released it and it is not printed due to a system failure, or the order has been put on hold.

XX = The Shop order is closed.

Previous Article BPCS/LX Tip of the Week: Work Center & Machine Locations
Next Article Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance
Print
55278 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Previously, a user was able to complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600.

This enhancement verifies the user security settings that were set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and complete the cost transfer process. This enhancement provides security in CST920 that prevents incorrect cost transfers from being processed.

Optimize Your Manufacturing Today!

This enhancement provides a method to post material, labor and overhead values on inventory postings to the general ledger to meet financial reporting requirements. The solution provides an optional further breakdown of cost by cost bucket using the new G/L Cost Type.

The benefit this program provides is the ability to post detailed material, labor, and overhead values during inventory posting to the general ledger to meet financial reporting requirements. It also helps isolate import and transport cost elements required by some countries. Global companies with intercompany purchasing are able to isolate material costs so that it is eliminated at a consolidated level.

Optimize Your Manufacturing Today!

First8283848587899091Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last