Infor LN & Baan Tips & Tricks for OPERATIONS: Order Quantity Dependent Routings vs Default Routings

Order quantity-dependent routings

An automatically selected routing tailored to a specific production order quantity is useful. An example would be if the production order quantity is large, a routing with high production rates is used; If the order quantity is small, another routing is selected.

You can set up these quantity-dependent routings:

  • Select the Quantity-dependent Routing check box in the Item - Production (tiipd0101m000) session.
  • Enter the routing codes in the Item - Routings (tirou1101m000) session. Enter the maximum quantity for which a routing is valid in the Up to Quantity field.

Note: If multisite functionality is activated, the routings available may vary per site on the job shop bill of material selected. Differences in routings have an impact on the standard cost calculation.

Default routing

If the Quantity-dependent Routing check box is not selected, the default routing applies to an item. However, this default routing must also be linked to the item. To find out, LN checks the default routing code in the Default Routing field of the Job Shop Master Data Parameters (tirou0100m000) session. Next, LN checks whether the default routing code is linked to the item in the Item - Routings (tirou1101m000) session. If so, the default routing applies to the item. If the default routing is not linked to the item, no routing is used.

Previous Article Infor LX/BPCS Tips & Tricks for OPERATIONS: Track all order holds added & released
Next Article Infor LX/BPCS Tips & Tricks for FINANCE: Default Billing Reason Code from User Order Class
Print
2988 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Sometimes the best ideas have to be tabled due to competing priorities. That doesn’t mean that the idea was bad. Revisit previously suggested cost savings ideas, or ideas to make a manual process more efficient. Now could be the right time to do something great!

Optimize Your Manufacturing Today!

 

This new feature provides the ability to resolve or reset a purchase order or requisition that is no longer being processed, but the system still indicates it is ‘in use’. We all remember those situations where we could never figure out how the order got hung up.

What we previously had to do was run a behind the scenes script to reset the flag so the order was again accessible. This enhancement provides the ability to resolve the issue and resume processes quickly.

This option is now on the PUR menu, and the user can select the Purchase Order/Requisition in Use Maintenance, PUR940D. The user then enters an order or requisition to remove the “In Use” status.

 

Optimize Your Manufacturing Today!

First9091929395979899Last

Theme picker

Tips: LN | Baan

Table Timestamp Definitions (ttadv4136m000)

Use this session to define timestamps for Infor LN tables. A timestamp is an additional column that stores the date and time of the last change for each record.

Timestamps are utilized by features like the extraction logic of CPM Enterprise Analytics. They enable CPM to perform incremental data extractions. For example, CPM can use the timestamps to extract records that were changed during the last week in a weekly extraction process.

To Create Timestamps...

Operations: To absorb the cost of cost items into specific projects, you'll need to handle them as customized items. However, cost items cannot directly be defined as customized items. Customized items must be physical, either manufactured or purchased.

That said, it's still possible to absorb cost items into a project, although indirectly. Here's how:

  1. Set Up Ledger Account: First, create a new ledger account in session tfgld0508m000 and set the type to "PCS" (project) in the operations management integrations. This account will be used for matching and approving purchase orders for cost items.

  2. Create and Activate Projects: Ensure that the necessary projects are created and set to active status.

  3. Purchasing Cost Items...

12345678910Last

Theme picker

Categories