Infor LX & BPCS Tip: Capacity Planning – Resource Requirements Reports

Resource Requirements Report (CAP260D) generates five capacity reports:

  • Labor Resource Requirements
  • Machine Resource Requirements
  • Setup Resource Requirements
  • Setup and Labor Requirements
  • Setup and Machine Requirements

The Labor Resource Requirement report lists requirements that are calculated from the run hours on each routing and the MRP/MPS demand in the Capacity Requirements Detail File (LCR). The calculation does not consider crew size.

The Machine Resource Requirement report lists machine hour requirements based on routings and the MRP/MPS demand in the Capacity Requirements Detail File (LCR).

The Setup Resource Requirements report lists setup labor requirements based on routings and the MRP/MPS demand in the Capacity Requirements Detail File (LCR).

The last two reports combine setup hours with labor hours and setup hours with machine hours to provide two separate reports that summarize the requirements by work center with totals by department. The system computes requirements similarly to the way it computes them on the other reports.

Have questions on this process or need some help? Contact us! Our experienced consultants will be glad to assist you.

800.762.2077

Previous Article 6 Ways Disconnected Data is Harming Your Business
Next Article Infor LN & Baan Tip: What is the GRNI Reconciliation Process?
Print
10218 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Job costing based on standards is great, but what if reality doesn’t match up to that?

What if jobs are really taking twice as long, and you don’t know that? What if jobs are taking ½ as long as you think, but you’re scheduling based on how much time they “should” take? Either way, you’re losing money and productivity. Getting a handle on start/stop times for jobs, and therefore the total amount of time actually spent allows you to take proper action and be more productive.

 

Optimize Your Manufacturing Today!

The Facility Period Close process was introduced in Infor LX 8.3.4 and has been enhanced in 8.3.5. This feature allows continuous or 24-hour worldwide operations in multiple facilities to submit Period End Close jobs for each facility as daily operations cease, or shifts end.

This enhancement provides a batch mode for the Facility Period Close (INV930) process and allows the Update IIM Inventory from IWI (INV931) process to be submitted from the INV930B program. The enhancement also provides a batch mode for the INV931 process.

Optimize Your Manufacturing Today!

First9394959698100101102Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements: