BPCS/LX TIP OF THE DAY: MATERIAL REQUIREMENT DATES AND LEAD TIME OFFSETS IN MRP

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Previous Article Infor LN 10.4.1 Release Notes
Next Article Key Solution Strengths For Process Manufacturers
Print
39974 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Job costing based on standards is great, but what if reality doesn’t match up to that?

What if jobs are really taking twice as long, and you don’t know that? What if jobs are taking ½ as long as you think, but you’re scheduling based on how much time they “should” take? Either way, you’re losing money and productivity. Getting a handle on start/stop times for jobs, and therefore the total amount of time actually spent allows you to take proper action and be more productive.

 

Optimize Your Manufacturing Today!

The Facility Period Close process was introduced in Infor LX 8.3.4 and has been enhanced in 8.3.5. This feature allows continuous or 24-hour worldwide operations in multiple facilities to submit Period End Close jobs for each facility as daily operations cease, or shifts end.

This enhancement provides a batch mode for the Facility Period Close (INV930) process and allows the Update IIM Inventory from IWI (INV931) process to be submitted from the INV930B program. The enhancement also provides a batch mode for the INV931 process.

Optimize Your Manufacturing Today!

First9394959698100101102Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last

Theme picker

Categories