BPCS/LX Tip of the Week: Multi-level Shop Order Release Due Dates

Previously, Material Requirements Planning (MRP) preferred practices meant that the component’s due date was the same as the parent’s shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The user is now able change how the due date is determined for multi-level shop orders. If the Due Date of Children parameter is set to 1=Yes, the due date of the child components is the same as the release date of the parent. If the parameter is set to 0=No, the due date is the day before the release date of the parent.

Optimize Your Manufacturing Today!

Previous Article Baan/LN Tip of the Week: How is Your Productivity?
Next Article Demand-Driven Manufacturing Metrics that Drive Action - White Paper
Print
27784 Rate this article:
5.0
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Sometimes the best ideas have to be tabled due to competing priorities. That doesn’t mean that the idea was bad. Revisit previously suggested cost savings ideas, or ideas to make a manual process more efficient. Now could be the right time to do something great!

Optimize Your Manufacturing Today!

 

This new feature provides the ability to resolve or reset a purchase order or requisition that is no longer being processed, but the system still indicates it is ‘in use’. We all remember those situations where we could never figure out how the order got hung up.

What we previously had to do was run a behind the scenes script to reset the flag so the order was again accessible. This enhancement provides the ability to resolve the issue and resume processes quickly.

This option is now on the PUR menu, and the user can select the Purchase Order/Requisition in Use Maintenance, PUR940D. The user then enters an order or requisition to remove the “In Use” status.

 

Optimize Your Manufacturing Today!

First9495969799101102103Last

Theme picker

Tips: LN | Baan

All actions required for converting, validating, matching, and posting electronically received bank statements can be performed within a single session:

  • Bank Statement Workbench (tfcmg5610m100)
  • Bank Statement (tfcmg5610m000)

Alternatively, you can use the sequence of electronic bank statement sessions outlined below.

Steps to Process Electronic Bank Statements:

12345678910Last

Theme picker

Categories