Infor LN & Baan OPERATIONS Tip: MPS Planned vs. MRP Planned

When deciding what items should be MPS (Master Production Schedule) planned and what items should be MRP (Material Requirements Planning) planned, it's crucial to understand the nature of the items and their demand sources. Here's a breakdown:

  • Master Scheduled Items:

    • Master Scheduled Items are typically finished goods or service items.
    • These items receive their requirements from both Independent and Dependent demand sources.
       
  • Independent Demand:

    • Independent demand cannot be calculated from higher-level demand in the product structure.
    • It is driven by forecasts or actual customer orders, primarily applicable to Finished Goods or Service parts sold to customers.
       
  • Dependent Demand:

    • Dependent demand is derived from higher-level demand in the product structure.
    • It includes components, raw materials, and sub-assemblies.
    • Dependent demand items are not typically part of Master Production Scheduling (MPS).
       
  • Service Parts:

    • Service parts can have both independent demand from forecasts or customer orders and dependent demand from higher-level demand if they are used in sub-assemblies or other products.
       
  • Cumulative Lead Time:

    • Cumulative Lead Time is a concept used in MPS.
    • It combines the fixed lead time and variable lead time required to produce a product.
    • It represents the longest path through a Bill-of-Materials (BOM).
    • Your ERP system will calculate the cumulative lead time (Critical Path) based on MPS setup options.
       
  • Infor LN Approach:

    • Infor LN does not differentiate between MPS and MRP planning.
    • It uses Enterprise Planning (EP) with one set of planned orders.
    • While you can set up items and generate orders at plan levels, it's not always necessary.
    • In theory, you could treat plan level 1 similar to MPS items.
       
  • Defining Independent Demand in LN:

    • In LN terms, independent demand is demand not related to other planned items.
    • Dependent demand comes from related planned items higher up in the BOM structure.
       
  • COLT (Cumulative Order Lead Time):

    • COLT exists in the purchase and manufactured planned items.
    • It considers non-critical and critical lead times based on components marked as critical.
    • Once calculated, COLT can be used to update the order and planning horizons of a planned item.

Relevant Sessions:

In Baan IV:

  • Maintain Item Data (tiitm0101m000)
  • Generate MPS (timps3201m000)
  • Maintain Master Production Schedule (timps3101m000)
  • Display Planned Inventory Movements by Item (timrp1510m000)
  • Display Planned MRP Purchase Orders (timrp1521m000)

In Baan V:

  • Plan Item Data (cprpd1500m000)
  • Item Master Plan (cprmp2101m000)
  • Time-Phased Overview (cprrp0520m000)

In Infor LN:

  • Item – Planning (cprpd1100m000)
  • Item Master Plan (cprmp2101m000) - Same as Master MPS if used


For more information and assistance, you can contact Crossroads RMC at 800.762.2077 or via email at solutions@crossroadsrmc.com.

Previous Article Infor LN & Baan TECHNOLOGY Tip: Are you running the latest Infor components?
Next Article Infor LX / BPCS Tips & Tricks for EXECUTIVES
Print
15156 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Role-Based Security introduces Role type profiles and allows combining the use of Role profiles with the traditional LX User type security profile functionality. The new Role type profile can be defined to allow or deny access to All Products, Attention Key, Products, Programs, and Transaction Effects. Facility, Warehouse, and Company securities are still defined solely by the User profile settings and are not affected by the assignment of a Role. Where applicable, the Role authority is displayed alongside the User authority on the security profile maintenance screens making it easy to see where there are differences in authority between the User and the assigned Roles. 

When Users are assigned to Roles, security access in LX becomes a combination of authorities granted or denied by the Role, plus any User Exceptions. User Exceptions override authorities set by the Roles. A User can also be assigned to more than one Role.

12345678910Last

Theme picker

Tips: LN | Baan

I know a lot of our customers are considering virtualization projects. I came across this, and thought it might be useful:

The advantages of virtualization include the following:

• You get more out of your existing resources. Pool common infrastructure resources and break the legacy “one application to one server” model with server consolidation.

• You can reduce datacenter costs by reducing your physical infrastructure and improving your server to admin ratio. Fewer servers and related IT hardware means reduced real estate and reduced power and cooling requirements. With better management tools, you can improve your server to admin ratio so personnel requirements are reduced.

• You can increase the availability of hardware and applications for improved business continuity.

• Securely back up and migrate entire virtual environments with no service interruptions. Eliminate planned downtime and recover immediately from unplanned issues.

 

• Gain operational flexibility. Respond to market changes with dynamic resource management, faster server provisioning, and improved application deployment.

The disadvantages of virtualization include the following:

• Virtualization adds overhead to the CPU, memory, IO, and network.

• Virtualization adds an additional layer to the hardware and software stack. Therefore, additional complexity is introduced in the following circumstances:

  • When sizing the physical server.
  • When planning VM capacity.
  • When planning multiple VMs on the same physical server.
  • When investigating performance issues.

 

You can set up interest invoicing in Accounts Receivable and in the General Ledger.

To set up interest invoicing, use these sessions:

Invoice-to Business Partner (tccom4112s000)
For invoice-to business partners for which you want to raise interest invoices, select the Charge Interest checkbox.

Mapping Scheme (tfgld4573m000)
Use this session to define the mapping of the Interest Invoice / Revenues Analysis integration document type.

Interest Percentages (tfacr5102m000)
Use this session to define the interest percentages for each financial business-partner group, and for different periods of days.

Interest Invoice Related Data (tfacr5101s000)
Use this session to define whether interest must be calculated on unpaid invoices, partly paid invoices, interest invoices, and/or fully paid invoices. You can also indicate that LN must take advance payments, unallocated payments, and credit notes into account for the generation of interest invoices.

Optionally, set conditions
Example: LN only generates an interest invoice advice entry if these conditions are met: The total of all advice entries in one currency is higher than the allowed minimum amount of an interest invoice defined in the Minimum Amount for Interest Invoice field.

The invoice is overdue for a greater number of days than the number of days defined in the Minimum Days for Interest Invoice field.

First96979899101103104105Last

Theme picker

Categories