BPCS/LX TIP OF THE DAY: MATERIAL REQUIREMENT DATES AND LEAD TIME OFFSETS IN MRP

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Previous Article Infor LN 10.4.1 Release Notes
Next Article Key Solution Strengths For Process Manufacturers
Print
38693 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Role-Based Security introduces Role type profiles and allows combining the use of Role profiles with the traditional LX User type security profile functionality. The new Role type profile can be defined to allow or deny access to All Products, Attention Key, Products, Programs, and Transaction Effects. Facility, Warehouse, and Company securities are still defined solely by the User profile settings and are not affected by the assignment of a Role. Where applicable, the Role authority is displayed alongside the User authority on the security profile maintenance screens making it easy to see where there are differences in authority between the User and the assigned Roles. 

When Users are assigned to Roles, security access in LX becomes a combination of authorities granted or denied by the Role, plus any User Exceptions. User Exceptions override authorities set by the Roles. A User can also be assigned to more than one Role.

12345678910Last

Theme picker

Tips: LN | Baan

If you do not wish to define a detailed mapping to various ledger accounts for specific integration transactions, you can map the corresponding integration document type to a default account. All the transactions of the integration document type for which an account cannot be determined based on the mapping scheme details, are posted to the default account.

 

The mapping of an integration document type to a default account is direct, without the need for element groups and mapping elements. No distinction is made on any of the transaction details.

 

Default accounts can be used in two ways:

  • Instead of a detailed mapping to various ledger accounts. All the transactions are posted to the same account. For example, all warehouse receipts are posted to the Inventory ledger account, without any distinction.
  • In addition to a detailed mapping. If a transaction cannot be mapped based on the detailed mapping scheme, it is posted to the default account.

A cluster is a group of one or more warehouses in a particular geographical area. You can plan an item by cluster (geographical area).

To enable this, you can set up multiple plan items for one item. You always define one plan item without a cluster indication and multiple plan items with a cluster indication. A plan item with a cluster is called a clustered plan item, and a plan item without cluster is called the non-clustered plan item.

The plan items in the clusters can be supplied not only by distribution, but also through purchase and production. In this way, you can, for example, plan local purchasing in a cluster (geographical area). You can also plan supply from multiple sources.

 