BPCS/LX Tip of the Week: Indirect Time Reporting

In Infor LX, there are two ways to enter indirect labor. You can use either SFC600 or SFC650.

  • If you use SFC600 and enter a reason code for the indirect labor, the reason you entered is written to the Labor Ticket file.
  • If you use SFC650 and enter a reason code for the indirect, the reason code is not written to the labor Ticket file.

In either case, the reason code is not validated from the transaction file because there is no indirect transaction code. The indirect code that can be setup is machine downtime. If you need to validate and track indirect by reason and validate the reason code, then you may want to explore an MES solution that works with Infor LX.

 

Previous Article Baan/LN Tip of the Week: Differences Between Constraint Planning in Baan IV and Enterprise Planning in LN
Next Article What You Don’t See Can Hurt You
Print
37331 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

TECHNOLOGY: Facility Security Ranges

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

FINANCE: Expiration Date for Quotes and RMAs

A Cancel-by-Date has been added to the Quote Header and RMA Header panels. This optional field can limit how long a quote or authorization to return items for credit is valid.  

For quotes, this enhancement provides an optional end date for the quote. For RMAs, it provides an optional date by which the customer must return the items to receive the credit listed on the RMA.

The Cancel-By-Date prints on the Order Acknowledgement and RMA Acknowledgement to inform the customer of this important limitation to the quote or return authorization. 

An Order Entry user cannot copy the quote to create a new order if the Cancel By Date has caused the quote to expire.

OPERATIONS: Default Split Salesperson to Customer Orders

Sales commissions are based on combinations of the Primary, Split, and Line-Level salesperson and the commission codes defined for the customer and item. You can now define the Split Salesperson in the same master files as the Primary Salesperson. While the Primary Salesperson is mandatory, the Split Salesperson is optional. It defaults during Order Create using the identical hierarchy as Primary Salesperson. Using Split Salesperson provides more flexibility in the calculation of sales commissions. The ability to define a default Split Salesperson improves the accuracy of sales commission qualification and calculation and reduces maintenance and adjustments necessitated by corrections.

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

12345678910Last

Theme picker

Tips: LN | Baan

A cluster is a group of one or more warehouses in a particular geographical area. You can plan an item by cluster (geographical area).

To enable this, you can set up multiple plan items for one item. You always define one plan item without a cluster indication and multiple plan items with a cluster indication. A plan item with a cluster is called a clustered plan item, and a plan item without cluster is called the non-clustered plan item.

The plan items in the clusters can be supplied not only by distribution, but also through purchase and production. In this way, you can, for example, plan local purchasing in a cluster (geographical area). You can also plan supply from multiple sources.

 

Optimize Your Manufacturing Today!

Do you have bottlenecks in your process due to product changeovers or breakdowns?

Maybe the answer is adding redundancy in the department where you are experiencing the problem. A duplicate machine setup can allow for double the capacity during high production periods. It can also eliminate the need to swap out tools or other materials due to different production runs. When breakdowns occur, equipment can be swapped out to keep production moving while repairs are being made.

Planning for this keeps production levels high.

 

 

 

Optimize Your Manufacturing Today!

First101102103104106108109110Last

Theme picker

Categories