Infor LX / BPCS Tip of the Week: Control Date Lead Times in LX

  • Control Date Lead Times – LX provides five separate Control Date Lead Time fields so you can specify additional lead time values for Shop Orders, Purchase Orders and Planned and Firm Planned orders. Each Control Lead Time Date represents additional time (days) required at each step in the process that needs more time (Quarantine, Stabilize), that is to say, when a component is due, and when it can be used. (working with an aerospace  precision bearing manufacturer, I had to account for the QA requirement that no measurements could be taken until the parts had been “soaked” (stored) in an atmospheric controlled environment (72 degrees, and controlled humidity) for 24 hours. This requirement added one full day of lead time between each machining operation) The MPS/MRP Generation program, as well as programs that Shop Order Material Allocation records use the five control date lead times to adjust component required dates to function in the same way as the BOM Offset Lead Time.
     
  • All programs that create MRP Planned Orders, MRP Firm Planned Orders, Shop Orders, and Purchase Orders call the Control Date Calculation program (MRP515B) to establish all five control dates. A Control Lead Time Date is used to adjust the component Required Dates data in the Material Requirements file (KMR), based on planned orders for a parent, and the FMA Required Dates data, based on shop order release dates for a parent.
Previous Article Partner News: How does Infor LN fit the industries that it serves?
Next Article Why should you look at OTTO? Let’s see what an OTTO customer has to say:
Print
31055 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Role-Based Security introduces Role type profiles and allows combining the use of Role profiles with the traditional LX User type security profile functionality. The new Role type profile can be defined to allow or deny access to All Products, Attention Key, Products, Programs, and Transaction Effects. Facility, Warehouse, and Company securities are still defined solely by the User profile settings and are not affected by the assignment of a Role. Where applicable, the Role authority is displayed alongside the User authority on the security profile maintenance screens making it easy to see where there are differences in authority between the User and the assigned Roles. 

When Users are assigned to Roles, security access in LX becomes a combination of authorities granted or denied by the Role, plus any User Exceptions. User Exceptions override authorities set by the Roles. A User can also be assigned to more than one Role.

12345678910Last

Theme picker

Tips: LN | Baan

Under intense cost pressures, quality is at risk at many manufacturers. These 10 tips can help you survive the competitive challenges ahead.

  1. Maintain your focus. Make a decision about the kind of company you are and stick with it. 
  2. Reinvent your products regularly. Suppliers who sharply differentiate their products fare the best. 
  3. Maximize your productivity and increase your speed through enhanced product and process design. Lean manufacturing focuses on production and its associated costs from a component's conception.

Poor performance indicators make for poor outcomes.

Companies today continue to tolerate and accept how labor and production information is recorded, and the reliability on that information is questionable. In addition to collecting labor and production information, there are many other pieces of information manually recorded from the shop floor.

A critical element of information for productivity throughput would be to examine how much time the work center or machine was actually up and running. Downtime is another critical element of data that is usually manually recorded along with a reason identifying what caused production to stop. If this information is not provided on a timely and accurate basis, then what good is it anyway? Forms are filled out, data may or may not be keyed to a spreadsheet, the forms are sorted and filed, but is anybody really looking at the information that was recorded? Think about the amount of time it takes to manage the manual collection of information from your shop floor. 

What would real time access to data mean to your organization?
The benefits:

  1. Real Time Production Visibility
  2. Reduced Paperwork Load
  3. Downtime and Scrap Visibility
  4. WIP Inventory Visibility
  5. Improve Efficiency, Capacity Utilization

Optimize Your Manufacturing Today!

First103104105106108110111112Last

Theme picker

Categories