Infor LX & BPCS Tip: MPS Planned vs. MRP Planned

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both.

  • Independent Demand: This refers to demand that originates from sources such as forecasts or actual customer orders. Items sold directly to customers fall under this category.
  • Dependent Demand: Derived from higher-level demand within the product structure, dependent demand comprises components, raw materials, and sub-assemblies. These items are not typically designated as Master Scheduled Items.
  • Service Parts may exhibit both independent demand, originating from forecasts or customer orders, and dependent demand, stemming from their use in other sub-assemblies or products.
  • A crucial concept in MPS is the Cumulative Lead Time, which combines fixed and variable lead times required to produce a product. It represents the longest path through a given Bill-of-Materials (BOM). In Infor LX (ERP LX), the system calculates the cumulative lead time, also known as the Critical Path, based on setup options. Utilize the "indented BOM" display in BOM300 to identify the item with the longest lead time. Additionally, you may need to use Action 21, Line Detail, to view the lead time ("L/T") for each item.
Previous Article Unlocking the Full Potential of Your LX/BPCS Investment - Embrace the Cloud for Enhanced Connectivity
Next Article ​Infor LN & Baan Tip: Determining What Data to Archive or Delete
Print
7774 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Previously, Material Requirements Planning (MRP) preferred practices meant that the component's due date was the same as the parent's shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower-level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The Multi-Level Shop Order Release, SFC5302, has a new parameter for shop orders. The Due Date of Children = Release Date of Prent (Due Date of Children) field allows the user to set the due date determined for multi-level shop orders.

This feature uses different exchange rates in the user's inventory processes by using new macros in Post Inventory to G/L, INV920D. INV920 used macros limited by the Override Exchange Rate parameter set on the book in Book Definition, CEA105D3. If the Override Exchange rate parameter is set to No, the macro uses the Rate Type of the Book. If the Override Exchange parameter is set to Yes, the macro uses the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Warehouse Company, Order Company, or the Book regardless of the Override Exchange Rate parameter in the Book.

12345678910Last

Theme picker

Tips: LN | Baan

Under intense cost pressures, quality is at risk at many manufacturers. These 10 tips can help you survive the competitive challenges ahead.

  1. Maintain your focus. Make a decision about the kind of company you are and stick with it. 
  2. Reinvent your products regularly. Suppliers who sharply differentiate their products fare the best. 
  3. Maximize your productivity and increase your speed through enhanced product and process design. Lean manufacturing focuses on production and its associated costs from a component's conception.

Poor performance indicators make for poor outcomes.

Companies today continue to tolerate and accept how labor and production information is recorded, and the reliability on that information is questionable. In addition to collecting labor and production information, there are many other pieces of information manually recorded from the shop floor.

A critical element of information for productivity throughput would be to examine how much time the work center or machine was actually up and running. Downtime is another critical element of data that is usually manually recorded along with a reason identifying what caused production to stop. If this information is not provided on a timely and accurate basis, then what good is it anyway? Forms are filled out, data may or may not be keyed to a spreadsheet, the forms are sorted and filed, but is anybody really looking at the information that was recorded? Think about the amount of time it takes to manage the manual collection of information from your shop floor. 

What would real time access to data mean to your organization?
The benefits:

  1. Real Time Production Visibility
  2. Reduced Paperwork Load
  3. Downtime and Scrap Visibility
  4. WIP Inventory Visibility
  5. Improve Efficiency, Capacity Utilization