BPCS/LX TIP OF THE DAY: MATERIAL REQUIREMENT DATES AND LEAD TIME OFFSETS IN MRP

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Previous Article Infor LN 10.4.1 Release Notes
Next Article Key Solution Strengths For Process Manufacturers
Print
39844 Rate this article:
No rating
Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

TECHNOLOGY: Facility Security Ranges

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

FINANCE: Expiration Date for Quotes and RMAs

A Cancel-by-Date has been added to the Quote Header and RMA Header panels. This optional field can limit how long a quote or authorization to return items for credit is valid.  

For quotes, this enhancement provides an optional end date for the quote. For RMAs, it provides an optional date by which the customer must return the items to receive the credit listed on the RMA.

The Cancel-By-Date prints on the Order Acknowledgement and RMA Acknowledgement to inform the customer of this important limitation to the quote or return authorization. 

An Order Entry user cannot copy the quote to create a new order if the Cancel By Date has caused the quote to expire.

OPERATIONS: Default Split Salesperson to Customer Orders

Sales commissions are based on combinations of the Primary, Split, and Line-Level salesperson and the commission codes defined for the customer and item. You can now define the Split Salesperson in the same master files as the Primary Salesperson. While the Primary Salesperson is mandatory, the Split Salesperson is optional. It defaults during Order Create using the identical hierarchy as Primary Salesperson. Using Split Salesperson provides more flexibility in the calculation of sales commissions. The ability to define a default Split Salesperson improves the accuracy of sales commission qualification and calculation and reduces maintenance and adjustments necessitated by corrections.

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

12345678910Last

Theme picker

Tips: LN | Baan

Want to increase your efficiency across your organization?

Is access to real time data important to you?

Take a look at how and where your information is stored. Do you have employees keeping separate spreadsheets or databases outside of your ERP?

Separate data silos means that information is not being shared between departments. This can hamper growth, and cut down on overall efficiency. Take a look at why these silos exist. Can something be done within your ERP system to avoid having to store the information elsewhere? Can an integration be created to allow the ERP to have exposure to other databases, or allow updates to occur between systems?

Need help figuring out where to start? Contact us. We’d be happy to help.

Optimize Your Manufacturing Today!

  • Print Sales Order History Information - all invoices processed through sales
  • Check Inventory Valuation - this should tie out to your inventory accounts
  • Print Integration Information - see all postings from WIP to finished goods
  • Print G/L Transaction Information - print specific transaction types for any GL account
  • Print Lot Control Information - will show where serial numbers were used

Optimize Your Manufacturing Today!

First114115116117119121122123Last

Theme picker

Categories