Infor LN & Baan Tip: MPS planned vs. MRP planned

What items should be MPS planned, and what items should be MRP planned…

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, your ERP will calculate cumulative lead time (also called “the Critical Path”) for you.

Infor LN does not differentiate between the two. Here, it is simply an enterprise planning EP with one set of planned orders. It is possible to set up items and generate orders at plan levels, but not necessary. In theory, you could make plan level 1 similar to MPS items.

Another way of defining independent demand in LN terms is that it is demand not related to other planned items. Dependent demand comes from related planned items above in the BOM structure.

COLT still exists both in purchase and manufactured planned items. It has both non-critical and critical lead times based on components set as critical. Once calculated it can be used to update the order and planning horizons of a plan item.

Relevant Sessions:

In Baan IV
Maintain Item Data tiitem0101m000
Generate MPS timps3201m000
Maintain Master Production Schedule timps3101m000
Display Planned Inventory Movements by Item timrp1510m000
Display Planned MRP Purchase Orders timrp1521m000

In Baan V
Plan Item Data cprpd1500m000
Item Master Plan cprmp2101m000
Time-Phased Overview cprrp0520m000

In Infor LN
Item – Planning cprpd1100m000
Item Master Plan cprmp2101m000 (same as Master MPS above if used)

Previous Article Avalara - AvaTax Integration to Infor LX, BPCS, Infor LN, Baan, and M3
Next Article Infor LN & Baan: What are your production orders telling you?
Print
30254 Rate this article:
4.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

TECHNOLOGY: Facility Security Ranges

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

FINANCE: Expiration Date for Quotes and RMAs

A Cancel-by-Date has been added to the Quote Header and RMA Header panels. This optional field can limit how long a quote or authorization to return items for credit is valid.  

For quotes, this enhancement provides an optional end date for the quote. For RMAs, it provides an optional date by which the customer must return the items to receive the credit listed on the RMA.

The Cancel-By-Date prints on the Order Acknowledgement and RMA Acknowledgement to inform the customer of this important limitation to the quote or return authorization. 

An Order Entry user cannot copy the quote to create a new order if the Cancel By Date has caused the quote to expire.

OPERATIONS: Default Split Salesperson to Customer Orders

Sales commissions are based on combinations of the Primary, Split, and Line-Level salesperson and the commission codes defined for the customer and item. You can now define the Split Salesperson in the same master files as the Primary Salesperson. While the Primary Salesperson is mandatory, the Split Salesperson is optional. It defaults during Order Create using the identical hierarchy as Primary Salesperson. Using Split Salesperson provides more flexibility in the calculation of sales commissions. The ability to define a default Split Salesperson improves the accuracy of sales commission qualification and calculation and reduces maintenance and adjustments necessitated by corrections.

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

12345678910Last

Theme picker

Tips: LN | Baan

Standard costing is really a ‘best guess’ at labor costing -- these numbers are often inaccurate, incomplete or out of date.

Accurate job costing requires the capture of all tasks associated with a specific product or job, including direct and indirect labor in setup, production and customer service.

Inaccuracies in the collection of time allocated to machinery and the use of materials can result in the inability to properly pass those charges through to the customer, reducing company profitability.

Basically, you can’t manage what you can’t measure -- and you can’t measure what you can’t track. So the inability to track time-to task ultimately inhibits maximum utilization of the workforce. Unproductive activities remain hidden from sight -- managers don’t have the information needed to understand where wasted time exists, and therefore cannot create an action plan to remove it.

Optimize Your Manufacturing Today!

  • Sit down with your IT team. Decide how the information will be captured and where it will be stored so that employees have access to it. What software tools need to be used to capture the information? How does it need to be organized? Create a repeatable process to make this easy for your staff.
     
  • Interview the person. Have them talk you through his/her job. What are the things they do every day? What are their biggest challenges? How do they overcome them? 
     
  • Have someone shadow the person for a week. Watch what they do and how they do it. Ask questions. Who does he/she interact with in their department? Outside of their department? Why?
     
  • Find out what tools he/she uses to perform their job? Are there spreadsheets?  Reports within your ERP / outside of your ERP? Separate stand-alone databases? Drawings? Websites? Why does he/she use them?
     
  • Video record how the person does their job. Is their technique critical to “doing it right” the first time and not ending up with a bunch of scrap that you can’t reuse?
     
  • Figure out if the person does anything special on a monthly, quarterly, or annual basis that might not come up during the observation period or interview. 
     
  • Map how he/she uses your business system and how that impacts the rest of the company. Understand both the “what” and the “why”. Without this, new employees may end up figuring out what they need to do, but never understand why they need to do it.

Optimize Your Manufacturing Today!

First115116117118120122123124Last

Theme picker

Categories