Infor LX & BPCS Tip: MPS Planned vs. MRP Planned

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both.

  • Independent Demand: This refers to demand that originates from sources such as forecasts or actual customer orders. Items sold directly to customers fall under this category.
  • Dependent Demand: Derived from higher-level demand within the product structure, dependent demand comprises components, raw materials, and sub-assemblies. These items are not typically designated as Master Scheduled Items.
  • Service Parts may exhibit both independent demand, originating from forecasts or customer orders, and dependent demand, stemming from their use in other sub-assemblies or products.
  • A crucial concept in MPS is the Cumulative Lead Time, which combines fixed and variable lead times required to produce a product. It represents the longest path through a given Bill-of-Materials (BOM). In Infor LX (ERP LX), the system calculates the cumulative lead time, also known as the Critical Path, based on setup options. Utilize the "indented BOM" display in BOM300 to identify the item with the longest lead time. Additionally, you may need to use Action 21, Line Detail, to view the lead time ("L/T") for each item.
Previous Article Unlocking the Full Potential of Your LX/BPCS Investment - Embrace the Cloud for Enhanced Connectivity
Next Article ​Infor LN & Baan Tip: Determining What Data to Archive or Delete
Print
7743 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Previously, Material Requirements Planning (MRP) preferred practices meant that the component's due date was the same as the parent's shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower-level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The Multi-Level Shop Order Release, SFC5302, has a new parameter for shop orders. The Due Date of Children = Release Date of Prent (Due Date of Children) field allows the user to set the due date determined for multi-level shop orders.

This feature uses different exchange rates in the user's inventory processes by using new macros in Post Inventory to G/L, INV920D. INV920 used macros limited by the Override Exchange Rate parameter set on the book in Book Definition, CEA105D3. If the Override Exchange rate parameter is set to No, the macro uses the Rate Type of the Book. If the Override Exchange parameter is set to Yes, the macro uses the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Order Company. This enhancement provides macros that use the Rate Type of the Warehouse Company, Order Company, or the Book regardless of the Override Exchange Rate parameter in the Book.

12345678910Last

Theme picker

Tips: LN | Baan

Common sense rules. We may not like them, but generally, they stand the test of time and should be followed. Here are 8 common sense rules related to inventory management published by Inbound Logistics back in 2007. They still hold true today. 

1. If you don' t know where you are going, no road will take you there. Enterprise resource management systems are designed to tell you about today' s inventory. With some work, you can also access information about past inventory. To manage inventory proactively, however, you must know projected inventory levels for the future.

2. Make what you can sell. An integrated Sales and Operations Plan will naturally take into account expected demand in its production plan. Inventory is not an independent variable - it is the direct result of demand and supply.

3. Sell what you can make. Too often, a disconnect exists between sales and marketing desires and the reality of production capabilities.

4. If you can' t sell it, stop making it. If demand for your product does not materialize, you need to identify that gap quickly to avoid a buildup of non-moving inventory. Numerous mechanisms can be put in place to identify such trends.

For tips 5 through 8 and more details into the other tips, click the button below to read the full article.