Infor LN & Baan Tip: Defining “Unavailability” in Infor LN

This topic describes the definition of temporary unavailability for resources in a calendar.

Use one of the following sessions:

  • Recurring unavailability
    For recurring unavailability, such as national holidays, define the recurrence in the Recurrences (tcccp0143m000) session. Add that recurrence to the applicable calendar and availability type in the Calendar Recurrences (tcccp0144m000) session, and clear the Available check box for the unavailable days.
    With calendar recurrences you define recurring exceptions in a calendar, and set a time schedule for daily, weekly, monthly, or yearly unavailable time in one action.
  • Unavailable days for all availability types
    To define occasional unavailability, such as a department trip, use the Calendar Non-Available Days (tcccp0119m000) session. What you define here applies to all availability types.
     
  • Unavailable days for a specific availability type
    To define unavailability for a single day, complete the following steps:
  1. Start the Calendar Working Hours (tcccp0120m000) session.
  2. Find the applicable calendar and availability type, and clear the Available check box for a working hours type on the relevant date.
  • Unavailable during a part of a day
    To indicate that part of a day is unavailable, use the Calendar Recurrences (tcccp0144m000) or the Calendar Working Hours (tcccp0120m000) session to specify the time intervals that are available. All other times are considered unavailable. You cannot directly specify an unavailable time interval.

If you defined unavailable dates in the Calendar Non-Available Days (tcccp0119m000) or the Calendar Recurrences (tcccp0144m000) session, in the Calendar Working Hours (tcccp0120m000) session, click Update Calendar.

Note:

  • Unavailability always applies to entire days. If the Calendar Working Hours (tcccp0120m000) session contains multiple time intervals for a single date, and the Available check box is cleared for some intervals and selected for other intervals on the same day, the entire day is unavailable.
  • A calendar recurrence that makes a day unavailable has no effect on the availability of that day in the parent calendar.


It is not useful to define a special availability type for unavailability, because Infor LN does not maintain and update the working hours and the capacity data of a calendar in the Calendar Working Hours (tcccp0120m000) session based on non-available availability types.

Previous Article “Sorry, boss. We can’t help you move the business forward.”
Next Article Infor ERP Tip of the Week: 5 Steps to Managing Sales Tax
Print
19283 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

TECHNOLOGY: Facility Security Ranges

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

FINANCE: Expiration Date for Quotes and RMAs

A Cancel-by-Date has been added to the Quote Header and RMA Header panels. This optional field can limit how long a quote or authorization to return items for credit is valid.  

For quotes, this enhancement provides an optional end date for the quote. For RMAs, it provides an optional date by which the customer must return the items to receive the credit listed on the RMA.

The Cancel-By-Date prints on the Order Acknowledgement and RMA Acknowledgement to inform the customer of this important limitation to the quote or return authorization. 

An Order Entry user cannot copy the quote to create a new order if the Cancel By Date has caused the quote to expire.

OPERATIONS: Default Split Salesperson to Customer Orders

Sales commissions are based on combinations of the Primary, Split, and Line-Level salesperson and the commission codes defined for the customer and item. You can now define the Split Salesperson in the same master files as the Primary Salesperson. While the Primary Salesperson is mandatory, the Split Salesperson is optional. It defaults during Order Create using the identical hierarchy as Primary Salesperson. Using Split Salesperson provides more flexibility in the calculation of sales commissions. The ability to define a default Split Salesperson improves the accuracy of sales commission qualification and calculation and reduces maintenance and adjustments necessitated by corrections.

Previously, a user could complete the Cost Transfer (CST920) process for any range of facilities regardless of their security settings established in SYS600. This enhancement verifies the user security settings set up in SYS600 before processing cost transfers for a range of facilities in CST920. If the user has authority for a facility range, but there are facilities within that range that are not authorized, the program skips those facilities and completes the cost transfer process.

12345678910Last

Theme picker

Tips: LN | Baan

Here are some issues that you might run into if you stay on an old porting set too long:

  • Incompatibility because of operating system patches
  • Printing issues because of out-of-date libraries
  • Potential performance issues if binaries are not updated
  • Updating third-party products may not be possible because of dependencies
  • Limited support from Infor
  • Issues with updating database software/patches because of dependencies (if the database is also running on the same server as the application)

Need help getting on a newer porting set? Let us know! We’d be happy to help.

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.