Infor LX & BPCS Tip: MPS Planned vs. MRP Planned

What items should be MPS planned, and what items should be MRP planned?
Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor LX (ERP LX) will calculate the cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.
Previous Article Infor LN & Baan Finance Tip: MPS Planned vs. MRP Planned
Next Article What are your production orders telling you?
Print
14198 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Role-Based Security introduces Role type profiles and allows combining the use of Role profiles with the traditional LX User type security profile functionality. The new Role type profile can be defined to allow or deny access to All Products, Attention Key, Products, Programs, and Transaction Effects. Facility, Warehouse, and Company securities are still defined solely by the User profile settings and are not affected by the assignment of a Role. Where applicable, the Role authority is displayed alongside the User authority on the security profile maintenance screens making it easy to see where there are differences in authority between the User and the assigned Roles. 

When Users are assigned to Roles, security access in LX becomes a combination of authorities granted or denied by the Role, plus any User Exceptions. User Exceptions override authorities set by the Roles. A User can also be assigned to more than one Role.

12345678910Last

Theme picker

Tips: LN | Baan

There can only be one correction period, and it must be the last period in the period table.

There can only be a correction period for Fiscal periods and not for Reporting or Tax. This period is used for the posting of the Automatic Balancing of Profit and Loss entries as well as any auditor adjusting entries that may be made outside the normal year. This allows you to print a trial balance and financial statements of period 1-12, for example, eliminating any of those adjusting entries.

If you have the Company Parameter (Balancing of Profit & Loss) set to Individual Accounts, then it is critical to have a 13th period to post those entries to. With this setting, the Automatic Balancing will zero out each individual P&L account in the last period. You want this to be period 13 and not period 12.

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.