Infor LX / BPCS Tip of the Week: Control Date Lead Times in LX

  • Control Date Lead Times – LX provides five separate Control Date Lead Time fields so you can specify additional lead time values for Shop Orders, Purchase Orders and Planned and Firm Planned orders. Each Control Lead Time Date represents additional time (days) required at each step in the process that needs more time (Quarantine, Stabilize), that is to say, when a component is due, and when it can be used. (working with an aerospace  precision bearing manufacturer, I had to account for the QA requirement that no measurements could be taken until the parts had been “soaked” (stored) in an atmospheric controlled environment (72 degrees, and controlled humidity) for 24 hours. This requirement added one full day of lead time between each machining operation) The MPS/MRP Generation program, as well as programs that Shop Order Material Allocation records use the five control date lead times to adjust component required dates to function in the same way as the BOM Offset Lead Time.
     
  • All programs that create MRP Planned Orders, MRP Firm Planned Orders, Shop Orders, and Purchase Orders call the Control Date Calculation program (MRP515B) to establish all five control dates. A Control Lead Time Date is used to adjust the component Required Dates data in the Material Requirements file (KMR), based on planned orders for a parent, and the FMA Required Dates data, based on shop order release dates for a parent.
Previous Article Partner News: How does Infor LN fit the industries that it serves?
Next Article Why should you look at OTTO? Let’s see what an OTTO customer has to say:
Print
30867 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Theme picker

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Role-Based Security introduces Role type profiles and allows combining the use of Role profiles with the traditional LX User type security profile functionality. The new Role type profile can be defined to allow or deny access to All Products, Attention Key, Products, Programs, and Transaction Effects. Facility, Warehouse, and Company securities are still defined solely by the User profile settings and are not affected by the assignment of a Role. Where applicable, the Role authority is displayed alongside the User authority on the security profile maintenance screens making it easy to see where there are differences in authority between the User and the assigned Roles. 

When Users are assigned to Roles, security access in LX becomes a combination of authorities granted or denied by the Role, plus any User Exceptions. User Exceptions override authorities set by the Roles. A User can also be assigned to more than one Role.

12345678910Last

Theme picker

Tips: LN | Baan

In Baan IVC, plan items on the lowest plan level were automatically actual items (not product families). All plan items on higher plan levels were product families.

The relationship between a product family and items on lower plan levels was defined in a planning bill of material.

In Infor LN, every family item must be defined in the Item Base Data module. A family item can exist on any plan level. The relationship between a family item and items on lower plan levels is defined in aggregation relationships.

Aggregation relationships in Infor LN are much more flexible than the planning bills of material in Baan IV. For example, users can define aggregation relationships between items on the same plan level.

Baan uses the company calendar in the following modules to determine the start and end dates for planned orders:

  • Master Production Scheduling
  • Material Requirements Planning
  • Capacity Requirements Planning (All three combined in a single planning module for Baan V and LN)
  • Shop Floor Control

The calendar provides the valid working days, number of shifts per day and the number of hours in a day.

Baan allows for a single calendar for the whole company or for a calendar for each work center.